Why we need to limit
hold harmless clauses
By Donald Croysdale
A
few weeks ago, The Daily Reporter chronicled the saga of how
a prime contractor and 19 subcontractors were denied prompt payment
for services performed in the demolition of County Stadium. After months
of delay, legal wrangling and mounting debts, a settlement was reached
and payments made. Exposing this dispute to public sunlight might have
been the catalyst that led to a successful result.
But as The Daily
Reporter aptly opined, "It never should have taken so long."
The prime contractor, prior to getting paid, was being asked to indemnify
and hold harmless another firm, which was responsible for identifying
asbestos in County Stadium, with whom it had no contract and no control.
That firms judgment apparently was that no asbestos was present.
When the demolition firm, though, discovered some asbestos, it immediately
stopped work and reported it. The demolition firm probably prevented
a much larger problem.
Just reward?
Yet when it came
time to get paid, the demolition contractors "reward"
for its diligence was a demand that it indemnify and hold harmless the
firm that missed discovering the asbestos in the first place. No payment
would be made either for the prime contractors work or for the
19 subcontractors who helped it until this "broad form" indemnification
and hold harmless clause was signed.
It is unfair, and
in our view should be against public policy, that a contractor be required
to indemnify and hold harmless other parties for their actions or possible
negligence. Yet that is precisely what a "broad form" indemnification
and hold harmless clause does.
In the County Stadium
case, if a claim were made against the firm that missed identifying
the asbestos, and if the demolition firm were to have signed the "broad
form" indemnification and hold harmless clause, then even if the
asbestos firm were judged to be 100 percent responsible for the error,
the cost of the claim could be passed on to the demolition firm and
its subcontractors for payment. These costs may have exceeded $1 million.
A long road
Asbestos claims
can go on for years and years. Recently, major multi-billion dollar
companies including U.S. Gypsum, W.R.
Grace and Owens Corning Fiberglas
have declared Chapter 11 bankruptcy from asbestos claims. Much smaller
contractors and subcontractors should be concerned, too, about being
wiped out by claims.
If, due to financial
pressure, a contractor signs a "broad form" indemnification
and hold harmless clause as a quid pro quo for getting a payment it
was fully entitled to it could lose everything.
This type of situation
almost did in a local underground contracting firm. Through no fault
of its own except possibly not recognizing the incredible risk of signing
a broad firm indemnification and hold harmless clause this firm was
presented with a $2.5 million bill, years after work was done,
from a company it had indemnified and held harmless. Only by an obscure
technicality did an appeals court and the
Wisconsin Supreme Court reverse a decision that would have wiped
the company out.
The construction
industry is recognizing that broad form indemnification and hold harmless
clauses are unfair and dangerous to sign. Two-thirds of the states now
ban and make unenforceable broad form clauses. In 1997, the American
Institute of Architects, in its model contracts, limited these clauses
to "narrow form." In simple terms, each party is responsible
for its own actions or negligence.
The American Subcontractors
Association strongly supports use of the 1997 AIA A401 and A201 model
contracts. In 1998, the Associated General
Contractors also revised its contracts to narrow form. The revised
AIA and AGC contracts are clearly a positive move for our industry.
Not there yet
Here in Wisconsin,
though, we have some work to do. While in 1978 we were one of the first
to recognize that these broad form clauses were inherently unfair, the
original statutes wording was deemed too ambiguous. This is why
situations, such as the underground contractors near miss and
the considerable payment delays for the County Stadium demolition work,
continue to plague contractors primes and subcontractors alike.
Contractual language
is complex. A phrase or two can alter a clause completely from one that
is acceptable to one that is risky and dangerous. Attorneys know the
difference, but many contractors, especially smaller contractors, might
not.
The prime demolition
contractor knew the difference, stood its ground and refused to sign
a broad form clause. Under current Wisconsin statutes, this contractor
and its subcontractors were pretty much stuck. They could either sign
a dangerous clause, risking their companies, or they could incur months
of delay, and potential financial disaster, from not getting paid.
This is a choice
that contractors should not have to make. As a matter of public policy,
broad form indemnification and hold harmless clauses should be unenforceable
in Wisconsin. Contractors are responsible for their own actions, but
they should not be forced to indemnify and hold harmless others.
The ASA is leading
a coalition of construction groups to restore the original intent of
the 1978 Wisconsin statute. We are grateful that payment for the demolition
of County Stadium was eventually made, but this type of dangerous stalemate
should not be allowed to hang over contractors heads. Its
time now for our industry to move forward restore contract fairness
for small and large contractors alike by limiting indemnification and
hold harmless clauses.
|
Main | Story Index
| Schedule
of Events |
Sites of Interest
| Daily
Reporter Main |
Questions or help?
Drop us a line
©
2001, Daily Reporter Publishing Company, All Rights Reserved.