Damage in waiting
Don't let costs
of delay snarl your business
Another
delay. At the owner's direction, the general contractor held up your
crew for a whole day because the owner changed its mind at the last
minute about where to house some telecommunications hardware.
Later that
month, you submit your invoice on time, including an adjustment in labor
plus costs for rented equipment you had to keep an extra day. Several
weeks later, you receive your check, but the extra costs caused by the
delay are conspicuously absent.
Scrawled
on a note in the envelope is: "No payment for delay items!"
The note also cites the paragraph of your subcontract with a "no
damage for delay" clause in it. You've been burned again.
Don't let
this scenario happen to you. An unmodified "no damage for delay"
clause often is a "scorched earth" contract term that aims
to keep you from recovering damages in a wide variety of situations.
A "no
damage for delay" clause in the subcontract can cause more "damage"
than you think. For example, some of these clauses make impossible the
price adjustments for costs created not just by delays, but also by
"obstructions," "hindrances" or even "performance
by others on the project that increases the cost of the subcontractor's
performance."
Fortunately,
even when one or more "no damage for delay" clauses exist
in the subcontract, most courts recognize that some circumstances are
unforeseeable, such as unexpected subsurface conditions. If the subcontractor
is not the cause of the unforeseeable circumstance, a court may judge
that the "no damage for delay" clause cannot be enforced.
Many state legislatures have limited the enforceability of "no
damage for delay" clauses through anti-indemnity and other laws.
Think
ahead
Of course,
you don't want to have to go to court to collect the money you are owed.
Sometimes litigation is the only option, but the adage, "An ounce
of prevention is worth a pound of cure," applies.
The easiest
way to help ensure that your subcontracts will not keep you from pursuing
additional direct costs caused by another contractor, the construction
manager, the architect or the owner is to include an exception letter
conditioning your bid on use of the American Institute of Architects
A401 document or making the subcontract subject to ASA's Addendum to
Subcontract. In paragraph 7, the Addendum provides: "
Subcontractor
shall be entitled to an equitable adjustment in the price of the work,
including but not limited to any increased costs of labor, including
overtime or materials, resulting from any change of schedule, acceleration,
out of sequence work or delay caused by others for whom Subcontractor
is not responsible
"
Using the
Addendum may be very advantageous because its language overrides all
language to the contrary, wherever it is in the amended subcontract.
Another
key to preserving your right to pursue delay claims is to ensure that
you always give required notice of delays or other problems as stipulated
in the contract. You may be penalized if you do not follow the contract
to the letter.
These are
just a few ideas to help improve the experience of getting paid for
extra labor, equipment rental and materials required on the job site.
ASA's Payment Advocacy Year Web
page contains many more ideas and payment resources.
This article
is provided in conjunction with ASA's Payment Advocacy Year.
|
Story Index | Members
List | 2003-04 Schedule |
| Special Sections Main | DailyReporter.com
|
©
2003 Daily Reporter Publishing Co., All Rights Reserved.