McGann adjusts schedule for Boys and Girls Club
 | McGann
is using a steel bar-joist roof for the Boys & Girls Club of Dane County project
in Fitchburg.
Photos courtesy of McGann Construction Inc. |
The
Boys & Girls Club of Dane County project was right on schedule. It was
June, and McGann Construction Inc. arrived on site ready to get started on the
21,200-square-foot, single-story, multiuse building. The plan was to build a facility
for neighborhood kids that would provide a gym, a commons room, a pantry, administrative
offices, a kitchen, a tech room, financial education offices, arts and crafts
areas, a music room, a teen room and a stage. But before McGann could get
started, the Madison contractor found itself in the middle of a tale of two cities.
With a parking lot in Madison and a building in Fitchburg, the project posed a
logistical problem. There were delays because the two cities were
concerned with what would happen if the nonprofit Boys & Girls Club went out
of business, said Wally Brey, McGanns job superintendent. Fitchburg
would get the building without a parking lot. It took Fitchburg and
Madison three months to give the project a green light, but that didnt necessarily
make the challenge any easier for McGann. Fitchburg hired McGann for the structure,
but Madison hired a separate contractor Speedway Sand & Gravel Inc.
of Middleton for the parking lot.  | The
Boys & Girls Club, with the building in Fitchburg and the parking lot in Madison,
poses a tricky challenge for McGann.
Photos courtesy of McGann Construction
Inc. |
And with two cities watching over the project,
McGann found itself doubling its efforts. Water goes through a road
in Madison, and sewer goes through a road in Fitchburg, Brey said. When
we patch the blacktop, well be patching some in Madison and some in Fitchburg.
Nobody likes pulling permits in the first place. Now, we have to
do it twice. The three-month delay, combined with slow going as the
construction team made the sites soil suitable for construction, forced
McGann to face a new list of challenges. What started out as a summer project
now had a lot of frost around the edges. And with cold weather comes additional
costs. Heating means that now when we lay block on the outside walls,
we have to tarp and heat it to protect the mortar, Brey said. We put
tarps over the scaffolding. It takes time, and it costs money. Itll be the
biggest challenge. But McGann has persevered, and, as 2005 draws to
a close, the contractor expects to have the new facility buttoned up. Despite
all the challenges, Brey said, the finished project will be worth the effort. When
were done, I think itll be a building we can be proud of, he
said. Itll be sharp. - Chris Thompson Project
SpecsProject Name: Boys & Girls Club of Dane County Location: Fitchburg
General
Contractor: McGann Construction Inc., Madison Architect:
Plunkett Raysich Architects LLP, Madison Estimated Construction Cost: $2.6 million
Start
Date: September 2005 Scheduled Completion: May 2006 Project
FactThe Boys & Girls Club of Dane County project uses 55,000 blocks and
200 tons of grout in the block. |
© 2007 Daily Reporter Publishing Co., All Rights Reserved.
|