Do the waive
Wisconsin's Building Commission has
its own limited-bidding game plan
By Jeremy Harrell
Well-known fact: Legislators, lobbyists
and trade associations are waging a high-profile battle over
the fate of design/build and limited-bidding for public projects.
 |
|
Sen.
Fred Risser
D-Madison
|
Little-known fact: The State Building Commission
has for 25 years authorized design/build, negotiated contracts and single-bid
prime contractors in the construction of public projects both large
and small.
The folks wrangling in Madison might want to take a few moments to look
up from the negotiating table to peek at the Building Commission's use
of alternative construction processes. The commission's approach to
waiving public-bidding laws, its members said, is to proceed with caution,
act on reason and respond to the specific needs of every project.
"The only time the Building Commission
should utilize design/build is when the staff can demonstrate
that there's no alternative," commission member Rep. Daniel
Vrakas, R-Hartland, said. "It should be used only in exceptional
situations."
Those exceptional situations are, by and
large, determined by three factors: size, time and ease. And
even when those factors are in evidence, the commission still
holds some reservation for deviating from traditional design/bid/build.
The Legislature granted the commission
the permission to waive public bidding as part of the 1975 budget
bill. In the 25 years since, the commission has invoked the waiver
approximately 125 times - a paltry number when compared to the
thousands of projects that have appeared on commission agendas.
Of those 125 projects, only on a handful
did the commission vote to proceed with design/build or some
other form of negotiated contract. And of that already small
sum, most were projects costing less than $1 million.
"We try to restrict the waiver to
small jobs," said Sen. Fred Risser, D-Madison, who has served
on the Building Commission for more than 30 years. "The
idea is that it becomes to the advantage of the state, the contractor
and all the people involved."
Single-source advantage
Wisconsin is one of the few states that
requires separate contracts for what ordinarily falls under the
jurisdiction of a general contractor. If the state wants to build
a new forest-ranger shed for the Department of Natural Resources,
it must by law bid out individual contracts for the carpentry,
the electrical, the HVAC, the cement foundation, and all other
aspects of construction for an otherwise unremarkable building.
By waiving the state bidding requirements, the Building Commission
can bid out the project to general contractors who take the various
subcontracts into account when making their bid to the Building
Commission, commission Secretary Bob Brandherm said.
"In general, we like to have a single
source of responsibility for smaller projects," he said.
"But just because we're waiving the bidding statute doesn't
mean we're waiving competitive bidding."
On those smaller projects - which tend to be no-brainers like
sheds, storage facilities and bathrooms at state parks - the
commission will sometimes award design/build contracts to make
the process even more simple and direct, Brandherm said.
The commission's frequent decision to waive
the bidding requirements on some projects has to some degree
come in response to complaints from contractors, Risser said.
State contracts entail a stack of paperwork, and the commissioners
have heard builders gripe that small jobs aren't worth the hassle.
"We've had a couple of cases where bidders wondered if they
were treated fairly," he said. "The waiver is basically
used where it's figured that bidding the contracts is minor.
In other words, it doesn't pay to bid out to multiple contractors."
... And step on it
As for the larger projects that employed
negotiated contracts or design/build, all were the result of
time considerations or some perceived specific need, Brandherm
said.
Take, for example, the Pettit Ice Center
on the state fairgrounds. The state found itself in the awkward
position of having to build a world-class ice rink in 10 months
because a private donor - who put up nearly a third of the $13.5
million price tag - insisted the project be completed by New
Year's Eve of 1991. Bidding the project out would have cost the
state the money it needed to build the project in the first place.
"It's much faster to develop a waiver because the statutory
process for developing bids takes longer," Risser said.
"Sometimes there's a presumed need to speed the process
up."
Going with design/build on a large project
when there's no time crunch works against the interests of the
state, Brandherm said. Private owners using design/build to speed
up the pace of a project tend to see their buildings' usefulness
in terms of its profit margins. They can cover the cost of construction
with seven to 10 years of occupancy, and sometimes they'll build
their facilities with that in mind. Wisconsin's government, as
Brandherm put it, will most likely be around in another 50 years,
and its buildings better be, as well.
"Each owner has different criteria
for deciding what needs to go into a building," he said.
"You have to compare the public's need for longevity with
the private sector's need for speed."
Vrakas said the state is obliged to competitively
bid out the most expensive and complicated projects because it
might otherwise end up paying more. The relative slowness of
the competitive bid process allows those vying for the contract
to iron out potential problems and associated cost increases.
"When a project is large and complex,
the Building Commission has a responsibility to bid the project
out," Vrakas said.
Commission members also said they have
to take design factors into account when voting to proceed with
a delivery system like design/build. There's the case of the
Government Executive Facilities in Madison. The oversized blocks
of poured concrete and light brick were constructed on design/build
contracts at a time when Madison general contractor Marshall
Erdman, an early proponent of the delivery method, served as
a citizen member of the Building Commission.
"The state went design/build on the
GEFs, and the state didn't have its hands on details like design
and selection of materials," Brandherm said.
For Vrakas, letting go of aspects of a
building's design is not, in most cases, worth the oft-stated
benefits of design/build.
"One of the potential problems with
design/build is you lose control of one step in the design process,"
he said.
As the people who control the state's construction
wallet, members of the Building Commission said they weren't
thrilled by the idea of tinkering with the design/bid/build tradition.
Rep. Robert Turner, D-Racine, said he worried
that going around the statutory bidding laws would shut minority
contractors out of the state's building projects.
"I've always found that the bidding
process is the only way to include minority contractors,"
he said. "Competitive bids make sure there's equity among
all the contractors."
Put another way, with the waiver, the State
Building Commission holds public construction's trump card in
its hand, but no one should expect the commission to play it
on whim.
"I think it's important we not expand
our usage of the waiver beyond what we've done to this point,"
said commission member Sen. Robert Wirch, D-Pleasant Prairie.
"Only in very certain areas is it warranted."
Harrell is The Daily Reporter's Madison
Bureau writer.