|
Under the hood
The anatomy of a design/build
project
By Jeremy
Harrell
Daily Reporter Staff
Proponents
of design/build talk frequently about the more tangible things the
delivery method can bring to a project, such as time and cost savings.
There are intangible
qualities, too, they say, such as a team approach that elicits the
best ideas from both the owner and the design/builders.
But what actually
happens on a design/build project that makes it so much different
than a conventional, low-bid job? To find out, The Daily Reporter
investigated a project performed by Green Bay general contractor
The Selmer Company.
Early stages
The project
began when team leaders from the Selmer Company sat down with members
of Christ the Rock Community Church in Menasha to develop a game
plan for building a new, vastly expanded church, said Tim Rinn,
Selmer's director of business development.
"They're
a nondenominational, community church, and they wanted something
less regimented than what you'd find in a Catholic or Lutheran church,"
he said.
As with all
of its design/build projects, Selmer officials conferred with the
owners to come up with a basic blueprint for the project. Within
a few weeks, Selmer, working with architect William Aubrey of Oshkosh-based
Architects / Engineers / Construction Managers, presented the owner
with a cost estimate, which Rinn said was within 10 percent of the
final project tally.
"We did
some hard numbers for them so they didn't go all the way down the
road only to be disappointed," he said. "We came back
with a detailed cost sheet-including subcontractor prices and labor
costs. The owner can then go to the bank and know if it's going
to be feasible."
Church leaders
agreed to the project scope, and Selmer engineers and surveyors
set about conducting topographical and wetland studies to find the
best piece of land. Selmer also did some pre-engineering work on
an existing building so the church leaders would have an array of
options, Rinn said.
After choosing
a site near Highway 10 in Harrison, Selmer, Aubrey and church leaders
worked for more than six months going over potential designs for
the new church, selecting materials and ditching ideas that were
either too costly or not right for the new building. During that
time, Selmer sent out potential bids to subs and suppliers so the
owners would have the most accurate, up-to-the-minute cost estimates.
"In
terms of budgeting, we laid out options for materials and different
designs," Rinn said. "We gave them a shopping list and
let them decide what they wanted."
Mike Morris,
project coordinator for glass and acoustic tile subcontractor H.J.
Martin & Son Inc. in Green Bay, said the collaborative approach
reduced potential friction because everyone was involved from the
beginning.
"Things
run smoothly when the owner gives the contractor the ability to
choose a team and work with the right people," he said. "It
gets the owner, the architect, the contractor and subcontractor
on the same page. And when you have 'thought-storms' together, you're
able to iron out a lot of the dilemmas."
Meanwhile, the
owners were still raising money for the new church, which meant
Selmer did a half-year's work for no pay, Rinn said.
"We did
the design work for free because that's part of the planning process,"
he said. "We get paid when we build-it's a reward for a job
well done. If we had ended up not building the project, then we
shouldn't be in business."
Digging in
As the design/build
team steadily narrowed the job's focus, Selmer got a clearer picture
of what materials and supplies would be needed. Ordering the materials
for the design/build job followed the same process as with a conventional
project, Rinn said.
The only difference
was that, in terms of some of the long-lead items like pre-cast
concrete panels and structural steel, Selmer could make some orders
before knowing precisely how much it needed.
"We approached
the owner to let them know about how much time it would take to
get certain materials," Rinn said, adding that this wasn't
a fast-track job. "After settling on an item, we knew we had
to get on everyone's schedule early in the year. If we didn't know
the exact dimensions and quantities, we just got on their production
schedule."
The weather
warmed up as the design process drew to a close, which pushed Selmer
to begin construction before the final plans were in place. Making
the orders for longer-lead items over the winter paid off as the
company started work immediately, Rinn said.
"We started
the site work before the final design was finished," he said.
"There was good weather-and good interest rates. By the time
the site work was finished, the aesthetic design was complete."
Selmer self-performed
the concrete, masonry, carpentry and steel erection trades. For
the rest of the subcontracting work, Selmer bid out some trades
and also relied on companies that were most responsive during the
project's planning stage, Rinn said.
Finishing up
After nearly
two years of planning and building, the 118,000-square-foot, $7.1
million Christ the Rock Community Church is nearing completion.
The church's sanctuary can seat more than 2,000 people, and it's
decked out with a complete stage with two large monitors built into
both sides of the large room. It's also got a state-of-the-art sound
system for musical performances-both for services and for other
events.
Attached to
the sanctuary is a day care facility, a recording studio for the
church's teens and administrative offices.
As the project
neared its end, the owners approached Selmer's project manager,
Mark Miller, and told him they wanted to shave some of the final
building costs in order to buy new furniture. So Selmer went back
to the members of the project team to figure out a way to save some
money.
"As
a team, we worked with our suppliers to reduce costs," Rinn
said. "We decided on things like different elevator paneling
and outdoor lighting. Because it's a team thing, you can get a lot
more out of your team members. A lot of times the owner wants to
make changes in the middle of a project, which would be cumbersome
and difficult with design/bid/build."
The cost reductions
saved the owners almost $400,000, he said.
Again, H.J.
Martin's Morris said that because his company had been involved
in the project early and gained familiarity with it, it was easy
to find ways to cut costs without compromising quality. And because
it involved no change orders, the switch to new materials went smoothly,
he said.
"It comes
to a point when you say, 'Do we need this big, expensive item?'"
Morris said. "By working things like that out, you get a better
project down the line. We're able to come in and tailor certain
items for the job."
In all, Rinn
said Selmer built the project for $67 per square foot and still
turned a tidy profit.
"We make
the same money either way," he said. "The difference is
that with design/build we established a relationship with them.
This industry
is built on repeat business and referrals."
Curt Drexler,
Christ the Rock's executive pastor, told the folks at Selmer that
he would gladly direct business the company's way after enjoying
such a collaborative experience.
"Building
projects of this size, by their very nature and complexity, test
the true commitment of any organization and its staff," Drexler
said in a letter he sent to the company. "The planning process
was the smoothest I have ever been a part of."
Rinn said the
design/build process really hinges on little faith.
"The owner
has to trust the people working on a design/build project, or else
it won't work," he said. "The owners who do trust us are
pleasantly surprised by what they get."
|
Editor's Note |
Story Index
| D/B Resources
| Books
| Main |
|
Special
Section Main |
Daily
Reporter Main |
Questions or
help? Drop us
a line
©
2001, Daily Reporter Publishing Company, All Rights Reserved.
|