Look out
below
By Steve Schultz
When a
contractor starts digging, perhaps the last thing he expects
to find is an environmental time bomb from the turn of the century,
right in the heart of the city.
But that
was the case in Waukesha in 1991, when a high-profile project
along the Fox River turned up blue-green soil that turned out
to be contaminated with cyanide.
The subsequent
teamwork by the contractors, the city and its consultants not
only brought the problem under control, but also serves as an
example of how a project deadline can be met even in the face
of an alarming discovery.
The project
was a new city park overlooking the Fox River, situated near
the regional headquarters for the state's transportation department.
The general contractor, Burkhart Construction Corp., contracted
out for the digging, and it was this subcontractor that struck
the unusually colored soil next to the bluffs of the Fox River.
"When
I got the original call that the contractor hit this blue material,
at first I didn't believe it," said Katie Jelacic, city
project engineer and the project's construction manager. "Then
I went there and saw this whole bucket was dyed a beautiful teal
blue."
Truckloads
of the blue-green soil were carted off-site to another city-owned
property before a consultant was called to identify the material.
"I
did a waste-profile analysis and found it was cyanide waste from
a manufactured-gas plant that operated there in the early 1900s,"
said James S. Drought, of Arcadis Geraghty & Miller Inc. in Milwaukee,
who worked for a different firm when hired for the soil analysis.
Made from coal, manufactured gas was burned in street lamps.
A contractor
who took initial soil samples at the site missed the contamination
because the cyanide was concentrated in one underground pocket,
Jelacic said.
Removal
of the soil was halted because transporting it was an unwitting
violation of Environmental Protection Agency requirements that
permits be obtained to move hazardous waste, Drought said. What
couldn't be stopped was the ticking of two clocks.
Deadline pressure
First,
the city had 90 days under hazardous-waste rules to move the
contaminated soil to an appropriate treatment facility. The nearest
one Drought could find was in Texas. Second, the city was committed
to opening the park in four to six months as part of a stated
goal to improve public access to the riverfront, Drought said.
What followed
was expeditious, effective and well-coordinated. A special contractor
was brought on board, and workers wearing protective clothing
and air tanks installed a temporary containment system over the
exposed waste, Drought said. Groundwater monitoring wells were
dug to determine if cyanide had leeched into the sandstone aquifer
from which Waukesha draws its drinking water (it hadn't), and
soil boring began to learn the extent of the contamination, he
said.
"We
didn't know if there was 100 tons, 1,000 tons or 10,000 tons,"
Drought said.
Burkhart
crews were relocated to work at safe areas of the large site,
and extra hand- and eye-wash basins were brought in, said Michael
Spanheimer, company vice president. City officials reassured
workers that the noncontaminated areas were safe, easing some
of the stress that could have existed at the scene, he said.
From start
to finish, from investigation to remediation, the process lasted
about 90 days, Drought said. Several hundred tons of contaminated
dirt was removed, at a cost of around $300,000, Jelacic said.
And the park opened on time.
"What
we learned was, in our type of construction, when we encounter
subsurface material that was really unforeseen, we always need
to be perceptive as to what we're involved with," he said.
"If anything looks different, we should pay heed and investigate
the material. That, more than anything, was driven home by this
whole process. We had something dissimilar, and I thank the Lord
that He allowed us to seek the proper direction."