
C.D.
Smith goes under the microscope | The
Microbial Sciences project team is working its way up from more than 50 feet below
grade.
Photos by Chris Thompson |
C.D. Smith
Construction has caught a lot of attention at the University of Wisconsin-Madison. When
a contractor digs a 140-foot-by-140-foot hole that's more than 50 feet deep in
the middle of the state's largest campus, people are bound to notice. When that
same contractor intends to fill the hole with the Microbial Sciences Building,
the second project of the $300 million BioStar Initiative, then people tend to
stop and stare. "It's a really high-profile job," said Gerald
Wheaton, C.D. Smith's project manager. "Is there extra pressure? No. We're
set to do quality work, and it doesn't bother us a bit being under the microscope." At
least a few members of the project team, Wheaton included, are used to being under
the microscope. When C.D. Smith won its $67.8 million portion of the project in
October, a group of people who had been working for the contractor on the Camp
Randall renovation moved over to the Microbial Sciences job. When C.D. Smith
arrived on site, the first step required digging out a footprint for the new structure's
four levels of underground parking. Working with Terra Engineering & Construction
Corp., Madison, the project team stuck its first shovels in the ground in January,
not the best time for earthwork. "It's wintertime in Wisconsin, you
know," Wheaton said. "You just have to deal with it. When they got dug
down deep enough, we started bringing it back up." PROJECT
SPECS Project Name: Microbial Sciences Building Location:
Madison General Contractor: C.D. Smith Construction Inc., Fond du Lac Architect:
Plunkett Raysich Architects LLP, Milwaukee Owner: University of Wisconsin-Madison
and state of Wisconsin Estimated Construction Cost: $104 million Start
Date: January 2005 Scheduled Completion: May 2007 PROJECT
FACT For it's Microbial Sciences Building project, C.D.
Smith removed 200,000 cubic yards of dirt and plans to use 31,000 cubic yards
of concrete. |
Wheaton said the project should reach
the surface by early June, at which point C.D. Smith will start to focus on the
seven above-grade stories of the structure. But it won't be easy. The project
sits on a tight spot, and Wheaton said he's already preparing for the challenges
that such a site creates. "The scheduling and sequencing will be difficult
tasks," he said. "There's no room to store anything, so we'll have to
bring it in and use it up." When the project reaches completion in
2007, the 400,000-square-foot building will let the university consolidate its
microbial sciences facilities under one roof. That finished product is already
a major factor in the project, Wheaton said. "This is early in the
game, and I fully believe with any project, if you can plan and make good judgments
in the beginning, you can save the project in the end," he said. -
Chris Thompson |