Concrete is Beautiful
After you see this place, you'll
never look at your garage floor the same way again.
By Steve Schultz
|

Photo: Jayne Laste; Click
on photo for larger image.
|
It looks like glop, but the stuff
has soul.
Most see a concrete mixer and think "new
driveway." Mark Wolf envisions the graceful lines of fine
architecture.
Wolf, the project executive for C.G. Schmidt Inc.'s concrete
division, studies a test pile of the gray gunk drying on a cardboard
box. The Milwaukee contractor is doing its own concrete work
in addition to being construction manager for the project.
As Wolf says, the Calatrava wouldn't have
possible without the most common building material around. But
the concrete being used to create the 125,000-square-foot addition,
and the formwork it requires, is anything but mundane.
Much of that planning was left to Wolf,
concrete finishers, carpenters and laborers that totaled 112
over the summer.
"I think it's really good that this
project gives a chance for the Milwaukee craftsmen to prove that
the skill level is comparable with, literally, some of the best
concrete work in the world," said Steve Chamberlin, president
of C.G. Schmidt.
And that work is truly the project's foundation.
The typical office building using poured-in-place concrete will
require the support of about 150 pounds of reinforced steel per
cubic yard, Wolf said. In certain areas that support the museum's
structure, the concrete will have about 800 pounds of steel per
cubic yard. Elsewhere, about 1,200 pounds of steel will be required.
Hold the ivy
But before cement trucks began rolling
in, it was the concrete work that gave project architects their
first shot at creating a new language.
"From an engineering standpoint, the
project is as complicated as any concrete building, probably
anywhere,"
|

A maze of rebar
supports the Calatrava's structure where concerete will soon
be poured.
Photo: James W. Brozek;
Click on photo for larger image.
|
said John Kissinger, a vice president
for engineer Graef, Anhalt, Schloemer & Associates Inc. and
the principal engineer for the addition. "That's not an
exaggeration in terms of some of the complexity of the elements,
just simple things like what to call them. Normally you have
beams and columns and girders. There are no such things on this
job."
It took months of planning before the mixers
rolled in. Architects and engineers joke that an ivy wall is
where there was a design mistake, but with Santiago Calatrava's
design, there will be nothing hiding the architect's vision.
"One of the biggest challenges is
that there's no second chances," Chamberlin said. "If
the form slips at all, you're done. It will be very noticeable
and very obvious."
Wolf points to the ring beam, a 293-foot-long,
58-foot-wide (and its widest point) oblong concrete beam at the
south end of the addition. In order to create it, 12 separate
pours were necessary.
"There were some aspects of the ring
beam that are so involved that the architect cannot even detail
them," Wolf said. "Some of the different areas of the
ring beam are actually handled by individuals from (Kahler Slater
Architects) that come out to the job site and work directly with
our foremen to try to explain, 'OK, this is what we want to create
in this area.' Kahler will come back the next day and say, 'Yeah,
that's what we want, just change this ..."
The right recipe
About a dozen different mixes concrete
are used -- with about half in the ring beam alone - to get just
the right creation at each section.
Some pours require a pump truck. Recently,
a six-inch steel pipe fed concrete through a tapered 3-inch nozzle,
enabling a 24-foot pour deep in the reinforced steel and post-tension
concrete.
Many walls are poured in layers, about
5 feet at a time, Wolf said. Crews complete one pour and move
on to the next, returning to add the next layer until the wall
is finished. Engineers constantly monitor the pours and remove
small samples in order to monitor how well it will cure on a
particular day. As a result, cardboard boxes with globs of concrete
are always nearby under careful scrutiny.
"There was a tremendous amount of
quality-control work," said Bob Peters, vice president of
operations for Central Ready Mixed Concrete L.P. "Basically,
we had to have people on most of the pours.
Back in the office
A C.G. Schmidt CAD technician examines
a computer-generated three-dimensional model of the museum.
"Our CAD technician dissected that
building on 1-foot increments, so that he was able to generate
a drawing showing every one of the gussets and built-forms, and
how every one of those built-forms had to be cut," Wolf
Photo: Jayne Laste; Click
on photo for larger image.
|
said. "The fact that mechanical
systems and pipes are built into the concrete structures made
it even more challenging, he said.
Computer-controlled lasers cut some of
the plywood forms, but on-site, creative C.G. Schmidt carpenters
used their own means to build forms. On the southeast side of
the structure, for example, exotic-looking concrete piers are
broad at bottom and narrow at the top. Carpenters created reveal
designs with a homemade plastic form.
Inside the structure, 78 concrete arches branch off a structural
backbone, each one a rib lending support as well as beauty. In
order to create them as perfectly as possible, engineers devised
a mobile pouring machine that was pulled along the floor, creating
a long hall of symmetrical designs.
"It's more organic." said David
Kahler, the principal in charge for the architect of record,
Kahler Slater Architects. Kahler said that building itself has
kind of skeletal structure. "A lot of the structural elements
basically replicate the skeletal elements you find in animals.
You don't have any straight lines, but compound curves."
Those curves must be duplicated exactly, he said.
The planning and craftsmanship has paid
off. There are few, if any, cold joints on the structure, where
concrete has hardened before the next batch was poured on top
of it. And air pockets are equally hard to find. Twelve external
vibrators have been used on the pours, because the mass of steel.
"It's so labor intensive to build
all that formwork, I'd hate pull that all off and find that you've
got one little thing (wrong)," Wolf said. "I think
that just about everybody who has worked on this job has learned
what little bit of effort it takes to provide higher quality."