Uncharted waters
The lakeside lines of The Calatrava
had no written plan
By Jack Bess
Many of the calatrava's
graceful lines were never sketched. "You couldn't get it
on paper," Owner representative Chris Smoke said. Instead
the means werer developed by engineers and craftsman on-site.
Photos on this page: James
W. Brozek; Click on photos for full image.
|
Like maps of old, where unknown parts
of the world were left blank, the design of the Milwaukee Art
Museum expansion contained at least one curved section that couldn't
be put down on paper.
That was at the east end or, as it is called,
the "east nose" of the building, where the football-shaped
concrete ring beam lies under the glass pavilion, said Jerry
Kaminski, the project executive a C.G. Schmidt Inc.
The architect went to the carpenters doing
the formwork for the concrete and told them he could not complete
the design of the curvature 6 feet from the tip, he said.
"The last 6 feet he just couldn't
do," Kaminski said. "He went out on the job and worked
with the carpenters, and they told him, 'We can do this or try
that.' So the design was completed in the field. There never
was a
drawing for that last piece on the east nose. You just couldn't
get it on paper. You just couldn't interpret what was happening."
So it's not surprising that Chris Smocke,
the owner's representative on the project, refers to venturing
into the project's uncharted territory as "pioneering."
"To do the process justice, it needs
to be characterized as working it out as we go," Smocke
said.
Construction pioneers
Clearly falling in the pioneering category
is the brise soleil, the movable sunscreen, which tops the galleria
and reception hall and is composed of carbon-fiber wings ranging
from 20 to 102 feet. "When we started, there was no machine
in the world to make what we needed to have," Smocke said.
"We needed to design and engineer a special machine just
to make the longest ones."
Tests were done to determine the right
material, the right thickness and weight of the material and
how the wings would connect to the spines. The overall configuration
of the brise soleil was given a wind-tunnel test in Toronto,
and the carbon-fiber used in the fins was being tested in Chicago
in early November, said Steve Chamberlin, president of C.G. Schmidt
Inc., the construction manager and the contractor responsible
for the concrete work.
"To be quite honest, sometimes we
don't know what the final solution is going to be and we don't
know what the desired result is as it related to the details
because it's never been done," Chamberlin said.
The project team is taking materials that
contractors work with every day-glass, concrete and steel-but
using them in innovative combinations and forms. As Kaminski
put it, "There are no straight lines here. Everything is
curved."
'Old World craftsmanship'
The lines of communication on the project
are unusual, too. Instead of the people at the highest organizational
level giving directives, there's a strong spirit of cooperation
and respect, with the designers and engineers seeking input from
the manufacturers and builders.
And that has worked. Sometimes the key
information on solving a problem comes from the craftsmen, Chamberlin
said. A good example of that occurred on constructing a concrete
pier with reveals, he said.
"The reveals have a radius, they're
curved and as you work your way from the bottom of the pier to
the top of the pier, each one has a different radius," he
said. "We actually had to build plaster models. We didn't
know the best
way to do it, but the carpenters figured out the best solution
to arrive at the desired look the architect was looking for."
Architects and
engineers weren't sure how to get the desired effect in parts
of the Calatrava's concrete structure, CG Schmidt President Steve
Chamberlin said. "We didn't know the best way to do it,
but the carpenters figured out the best solution to arrive at
the desired look the architect was looking for."
Photo: James W. Brozek;
Click on photo for larger image.
|
"It's like the Old World craftsman
who used to be able to do the fancy woodwork or plaster in old
churches, Kaminski said. "You need the tradesman to work
with the architect in many cases to solve how something is going
to be done."
Those associated with the project will
note that the whole project is like a sculpture, and that each
piece of the project is a sculpture also. Each piece of unusually
shaped concrete has a corresponding piece of unusually shaped
reinforcing steel inside it. And the "soaring concrete elements
that are cantilevered out 100 feet" takes an unusual amount
of reinforcing steel to hold it up.
Chamberlin said the workability of the
concrete was tested by building a sample concrete arch, and that
tests were also done to make sure the wet concrete could penetrate
all throughout the uniquely curved wooden forms.
"That's where you need a special mix
design," Chamberlin said. "You need ways to vibrate
the forms and ways to, in some case, to visually check it by
drilling holes as you move up the forms to be absolutely sure
you have full penetration of the concrete and that it structurally
and visually checks out. There's no second chance. It has to
be right."
Each portion of the project poses its own
challenge, and sometimes the challenge comes not only in construction
but also in the sequence in which things are built.
"Santiago (Calatrava) designs things
in balance but the structures are not really stable until they're
100 percent done," Kaminski said. He added, with a laugh,
"If you have a 10-story building and after three floors,
you can quit if you want. But in this case, you can't quit at
any point because until you get the whole structure up, it's
it in balance."
An example of this can be found in the
interaction of the ring beam and the bridge, Kaminski said. Workers
can't complete the bridge until the ring-beam concrete is poured
and tension is posted in the concrete, Kaminski said, because
posting tension will "pull the bridge back a certain amount,
maybe a half-inch. But until you do that, you can't do the final
piece on the bridge.
"You know the old adage, 'When you
come to work, you leave your brain at the door and just do what
you're told.' This is the exact opposite," Kaminski said.
"We need people thinking all the time."