There's a small city in Glendale where a mall used to
be.
That's the magnitude of the job performed by the project team that replaced
a nearly 50-year-old shopping center with the Bayshore Town Center.
The
47-acre project more than doubled the square-footage of the old structure, combining
restaurants, retail, housing and open areas within the Bayshore borders.
During
nearly two years of construction - while the mall remained open - more than 1,000
workers were on site during peak construction time, erecting 12 new buildings
in tight spaces. It took more than 3,000 people over the course of construction
to complete the job.
"It was a monstrous project," said Tim Van
Dyn Hoven, vice president of Hunzinger Construction Company. "It was the
largest commercial project in the state for two years running."
Just
planning the project took about a year. It was originally scheduled to take three
years to complete, but the schedule shrunk to just 22 months.
Despite the
resulting scheduling difficulties and the need to manage so many people and activities
at once, the whole project went well, Van Dyn Hoven said.
Project
Names: Bayshore Town Center and Bayshore Town Center North Parking Structure
Location:
Glendale
Submitting Companies: Corna Kokosing Construction Co.
Inc., Westerville, Ohio, north parking structure; Hunzinger Construction Company,
Brookfield, Bayshore Town Center; The Spancrete Group Inc., Waukesha, north parking
structure; Steiner + Associates, Columbus, Ohio, Bayshore Town Center
General
Contractor, Design/Builder: Corna Kokosing Construction Co. Inc., north parking
structure general contractor; Hunzinger Construction Company, Bayshore Town Center
design/builder
Project Leaders: Dick Dei, Corna Kokosing's project
manager; Brian Forston, Spancrete's project manager; Dwayne Furukawa, Steiner's
vice president of development; James Hunzinger, Hunzinger's project executive;
John McCarty, Corna Kokosing's project executive; Tim Van Dyn Hoven, Hunzinger's
vice president
Architects: Development Design Group Inc., Baltimore,
Bayshore Town Center design architect; Eppstein Uhen Architects Inc., Milwaukee,
Bayshore Town Center architect of record; Meacham & Apel Architects Inc.,
Dublin, Ohio, north parking structure architect
Engineers: Graef,
Anhalt, Schloemer and Associates Inc., Milwaukee, Bayshore Town Center civil,
structural, mechanical, plumbing engineer; HNTB Corp., Milwaukee, Bayshore Town
Center civil engineer; Jezerinac Geers & Associates Inc., Dublin, Ohio, north
parking structure engineer; Powrtek Engineering, Waukesha, Bayshore Town Center
electrical engineer
Owner: Bayshore Town Center LLC, Columbus, Ohio
Project Costs: $300 million for Bayshore Town Center; $41 million
for north parking structure
Project Sizes: 1.1 million square feet
for Bayshore Town Center; 600,000 square feet for north parking structure
Start
Dates: December 2004 for Bayshore Town Center; July 2005 for north parking
structure
Completion Date: November 2006
"It took a lot of men, a lot of activity and a lot of horsepower,"
he said. "Teamwork, planning and good execution - that's how you get it done."
But
getting it done wouldn't mean as much if Bayshore customers didn't have a place
to park. The center's new buildings went up where the mall's parking lots used
to be, and replacing those lost stalls with parking structures was a priority.
Brian
Forston, project manager for Spancrete, which made the precast parts for Bayshore's
north parking structure, said his team's biggest challenge was accommodating design
changes within a tight schedule. Massive concrete pieces for the parking structure's
façade and interior were cast in Spancrete's plant and then shipped to
the site for installation.
"The design was a moving target,"
Forston said. "Ours was set in concrete once we started."
John
McCarty, project executive with north parking structure general contractor Corna
Kokosing, said the job was a challenge, mainly because of time constraints.
"We
didn't join until later in the process," he said. "The actual [parking
structure] façade design was not completed until a few months before completion."
It
was the first time his company worked on a structure that combined retail, parking
and residential in the same building.
"I think it came out very well,"
he said. "It was on time and within our estimate."