What does it take to build a 60,000-square-foot computer
facility in record time? A virtual 60,000-square-foot computer facility, of course.
The construction team for the new State of Wisconsin Data Center in Madison
learned quickly that creating a virtual building before it actually goes up can
save a lot of time in the long run.
"The 3-D model allowed us to visualize
how to bring major equipment into the building," said Mike Sorge, M. A. Mortenson's
senior superintendent on the job. "We planned what walls and pipes we needed
to keep out. We were 75 percent complete with mechanical systems by the time the
equipment showed up."
The new center houses the Wisconsin Department
of Administration's Division of Enterprise Technology and consolidates computer
systems from multiple centers in the state. Considering the technological nature
of the building, it's only fitting that the center's construction set a precedent
for future state jobs as one of the first to use a 3-D building model.
The
construction team might be happy with the impact the virtual building had on the
construction process, but that doesn't mean it was an easy idea to get off the
ground. Initial coordination meetings took a long time, and not everyone was convinced
of the benefits of the 3-D program.
Project
Name: State of Wisconsin Data Center
Location: Madison
Submitting
Companies: Eppstein Uhen Architects Inc., Milwaukee; M. A. Mortenson Company,
Brookfield
Construction Manager/General Contractor: M. A. Mortenson
Company
Project Leaders: Ben Goetter, Mortenson's project manager;
Peter Kucha, Eppstein Uhen's architect; Mike Sorge, Mortenson's senior superintendent
Architect: Eppstein Uhen Architects Inc.
Engineer: Affiliated
Engineers Inc., Madison
Owner: Wisconsin Department of Administration,
Madison
Project Cost: $15.5 million
Project Size:
60,000 square feet
Start Date: October 2005
Completion
Date: April 2006
But when construction began, the members of the team came together.
"There was very little rework," Sorge said. "Things clicked.
Most became believers."
That's a good thing because the job had to
reach completion in an eight-month window. And that time frame, Sorge said, was
the biggest challenge.
"The building structure and enclosure is very
simple," he said. "But a lot of electrical and mechanical work had to
go into it in a short amount of time."
The center's computer room was
built over a 6-foot access floor to house all the power cabling. The space provides
air supply and maintenance access, and the 3-D model allowed for pre-fabrication
of components and early planning of the system's complex power sources.
"It's
a glorified machine room," said Peter Kucha, project architect for Eppstein
Uhen Architects. "The main challenge was working with the design team, construction
team, owner and end user to address concerns of all parties and deliver it within
the time frame."
Those concerns were minimal once the job got rolling.
"Out
of the thousand conflicts we identified during the model, we only had three conflicts
in the field," said Sorge. "Those were situations where the pre-fabrication
happened before we had signed off on the coordination of the model."