Editor's Note
Winners
Sites of Interest
Special Sections Main
Daily Reporter Main

It's all Academic

New chemistry building posed host of challenges

School

The new research tower creates a completely new presence for the University of Wisconsin-Madison Chemistry Department on this busy campus thoroughfare. The work site was so small that J.P. Cullen & Sons Inc. had to place extra material and equipment at the nearby United Methodist Church.

Photo courtesy of Flad & Associates

Project Name: University of Wisconsin-Madison Chemistry Building

Location: Intersection of Johnson and Charter streets, Madison

Owner: State of Wisconsin

Architect: Flad & Associates, Madison

Engineer: Flad Structural Engineers, Madison (structural); Affiliated Engineers Inc., Madison, and Kapur & Associates, Madison (mechanical, electrical and piping); Barrientos & Associates Inc., Madison (civil); Soils & Engineering Services Inc., Madison (soils)

General Contractor/Construction Manager: J.P. Cullen & Sons Inc., Janesville

Project Cost: $29.3 million

Start Date: May 1999

Completion Date: November 2001

Description: The general contractor had to squeeze the 184,000-square-foot chemistry building into a tight, urban site. Cullen's greatest challenge was devising a system to construct a 156-foot-tall precast, concrete shear wall that juts out 17 feet over the entrance to the building.

It took J.P. Cullen & Sons an awareness of its surroundings, a little help from a neighbor and a whole lot of ingenuity to complete the University of Wisconsin-Madison's new chemistry building.

Work on the new seminar hall and seven-story addition to the chemistry tower took place on a site pinched by heavy traffic on Charter and Johnson streets in Madison. There was a minimal staging area with work occurring within 15 feet of the property line and traffic on two sides.

To meet the challenge, Cullen turned to the nearby United Methodist Church to accommodate material and equipment overflow. Despite the tight site, Tom Pertzborn, Cullen's project manager, said the construction team treated the job just like any other.

"The site was typical of downtown construction," he said.

Working in such a constricted area required a high level of communication and sequenced installation of materials. Everything from crane use to material-delivery times was carefully scheduled to ensure adequate space for safe work conditions.

Project scheduling and coordination were even more complex tasks because -- considering that the tower houses 40 research labs and 128 fume hoods -- mechanical and electrical contractors had an extensive amount of work to do on each floor.

Close quarters

The tight space wasn't just evident on the ground. Workers who installed the 156-foot, precast, clad-concrete shear wall on the Johnston Street side of the site required elaborate scaffolding within the small available space. That wall juts out 17 feet over the entrance to the building.

The shear wall makes the new tower appear thinner, and the building is taller than the surrounding structures.

"This allows the exhaust from the chemistry building to release over the surrounding buildings," said David Black, project architect.

Cullen also faced a tight spot when erecting a wall of the new tower that had to be built 2 inches from the wall of an existing tower.

In order to accomplish the feat, Cullen created a one-sided form system to pour concrete for the wall. A crane slid the form up over the wall when it was completed.

"It takes a bit of ingenuity on the field supervisor's and foreman's part," Pertzborn said.

Pertzborn said the process included a learning curve, but by the time they were to the top of the wall, they had the system figured out.

Better conditions

The completed, 184,000-square-foot, state-of-the-art building provides new graduate research labs and support space, an instrument center and imaging facilities.

The new tower also facilitates synthetic-chemical research labs, which were moved to the new building because of its 16-foot span from floor to floor. The hazardous materials handled in these labs needed more air circulation than the 12-foot dimensions in the older tower.

The new labs create a different setting for researchers than in the old building. Researchers are in an observatory space separate from the lab, and a glass-wall partition allows them to view experiments from a safe distance.

"It's a relatively new approach to research labs," Black said.


| Editor's Note | Winners | Sites of Interest |
| Special Sections Main | Daily Reporter Main |

© 2002 Daily Reporter Publishing Co., All Rights Reserved.