Perfect Pitch
Miron strikes
chord with Resch Center
Resch
Center Arena Green Bay
By Jeremy
Harrell
Miron
Construction Co Inc., Neenah, has established its name as a general
contractor in Wisconsin, but after building the Resch Center in Green
Bay, the company can add large-scale piano tuner to its résumé.
The project
presented the first cable-structure arena for a secondary market in
the country, meaning the roof's membrane is hoisted into place and held
in check with large metal wires. The cables form a network under the
roof, and the tension on each had to be calibrated precisely to the
weight it's supposed to carry, said Royce Alsbach, Miron's project manager.
But when
wrenching one cable into harmony, the others would invariably fall into
discord, he said. To reach perfect pitch, the company would essentially
bang a cable with a large hammer and, using a computerized gauge, determine
if it was stretched to the appropriate level, Alsbach said.
"It
was like trying to tune a piano," he said. "We'd tighten one
cable up, and that would loosen another up. We had to adjust the cables
three times."
Tight
spot
Believe
it or not, that was only one of many significant challenges the construction
team faced during the nearly two-year project, which brought a big-time,
11,000-seat arena to Wisconsin's third largest city. The first hurdle
was the site itself, which was blocked on two sides by existing structures,
Alsbach said.
Miron,
which won the project through a hard bid, compensated by working the
project from the inside out. The company brought two large cranes into
the interior of the seating bowl, erected eight false work towers to
support the roof structure and jacked the pieces, starting with a linchpin
centerpiece, into place one by one, Alsbach said.
"The
roof structure was something we'd never seen before," he said.
"Most arenas are built with a box girder system. This cable system
eliminated the box girders, so you reduced the amount of steel and reduced
the space that had to be climate controlled."
|
Project
Name: Resch Center Arena
Location: Green Bay
Submitting Company: Miron Construction Co. Inc., Neenah
General Contractor: Miron Construction Co. Inc., Neenah
Architect: DesignStrategies LLC, Greenville, S.C, as a
consultant to O'Dell Associates Inc., Greenville, S.C.
Engineer: Geiger Engineers, Suffern, N.Y. (Structural);
SSR Inc., Houston (Mechanical)
Owner: Brown County
Project Cost: $45 million
Start Date: October 2000
Completion Date: August 2002
|
On the
exterior, architects with DesignStrategies LLC, Greenville, S.C., working
as a consultant to O'Dell Associates Inc., Greenville, S.C., designed
a serpentine glass curtain wall that serves as the arena's main entrance.
Again not taking the easy way out, the architect chose to attach the
curtain wall to structural steel rather than the typical aluminum framing.
The engineers
and Miron's project staff attuned the steel to the glass' tolerance,
ensuring there would be no "weeping" as the arena ages.
The guiding
principle for the whole project was cost-efficient design. The owner
paid $45 million for a project that in other cities could have cost
$150 million, Alsbach said.
"It's
a very economical and very sound design because it's a very durable
building for the price," he said.
That was
especially important because the project represented a pooling of resources
among several local governments in Brown County, said Ken Betsch, project
architect with DesignStrategies.
"It
was one of the best examples of intergovernmental cooperation I've seen
in my career," he said.
At the
height of construction, the project's work force peaked at more than
150 tradespeople who logged 500,000 hours of work. Remarkably, there
was no lost time due to injury, and Miron completed the project on schedule
and within budget, Alsbach said.