Taking Flight
Airport expansion
succeeds despite 9/11
Outagamie
County Regional Airport Greenville
By Chris
Thompson
The
logistics involved in expanding an airport concourse can give any project
manager a headache.
Throw in
the backlash of federal regulations following the Sept. 11, 2001, terrorist
attacks, mix them with a complicated expansion layout, and the project
could be a nightmare waiting to happen.
But in
the case of Miron Construction Co. Inc.'s work expanding and remodeling
the Outagamie County Regional Airport in Greenville, the results were
more like a dream come true. The Neenah general contractor added 49,000
square feet and eight gates to the airport's concourse and remodeled
30,000 square feet of the existing facility.
And it
did it in the midst of the tightened security following Sept. 11.
"9/11
happened while we were under construction," said Tim Kippenhan,
Miron vice president. "Everybody had to have badges, and there
were fingerprinting and background checks for everybody through the
FBI. The airport always had this, but not to this extent."
That was
just the tip of the security lockdown. All of Miron's material deliveries
had to pass through monitoring gates, and portions of the project design
were kicked back to the federal government for reinspection.
The proposed
drop-off and pedestrian canopy at the entrance to the airport, for instance,
had to go through federal review because of new restrictions involving
airport parking and loading zones, Kippenhan said. But even with the
four-month delay awaiting federal approval of the canopy, he said Miron
finished the $12.3 million project two months ahead of the contractual
completion date.
"We
took it in stride," Kippenhan said. "The coordination between
the county, the airport representatives and the contractors was extremely
great. It could have been real difficult."
Design
challenges
Sept. 11
security issues aside, the project posed a host of challenges for Miron.
The curved design of the expansion kept the contractor from finding
a right angle to anchor the construction. As a result, it all came down
to focusing on layout points.
|
Project
Name: Outagamie County Regional Airport
Location: Greenville
Submitting Company: Miron Construction Co. Inc., Neenah
General Contractor/Construction Manager: Miron Construction
Co. Inc., Neenah
Architect: Mead and Hunt Inc., Madison
Engineer: Mead and Hunt Inc., Madison
Owner: Outagamie County
Project Cost: $12.3 million
Start Date: May 2001
Completion Date: October 2002
|
"The
most difficult thing with this project is there isn't a single square
corner in the building they're all rounded," Kippenhan said.
"So the amount of layout was extremely difficult. All of the foundations
are on radial lines, so it's not a rectangular building at all.
"It
was an extremely difficult structure both in pouring the concrete and
erecting the structural steel," he added. "There was a real
attention to detail. It was a lot more labor intensive as far as doing
the layout."
The end
result, Kippenhan said, was worth the effort. The new concourse mirrors
the circuitous route of the nearby Fox River, and the south-facing windows
and skylights flood the addition with natural light.
"It's
a first-class facility, and it's important to give a good first impression
of the Fox River Valley," Kippenhan said. "We're extremely
proud of what was built."
But that
doesn't mean it was easy.
"It
was an extremely difficult project from a logistical standpoint and
Sept. 11," Kippenhan said. "We're proud it will stand there
for the next 30 years, and our name is associated with it."