
Mount
Pleasant Storm Water Utility District Pike River RestorationCrispell-Snyder
saves the PikeBy Rebecca R. Konya The
Pike River restoration project in Mount Pleasant is more than just a flood-control
project.
The first phase of the job, completed in May 2003,
provides nearly 15 acres of new floodplain with a restored ecosystem and nearly
80 acres of environmental corridor for public enjoyment. "The
improvements to the river system represent a sustainable approach to watershed
management," said Todd Weik, a senior project manager for Crispell-Snyder
Inc., which served as the engineer on the project. The multiphase
restoration plan features improvements along about five miles of the Pike River,
which drains a watershed of about 17 square miles within Mount Pleasant. Weik
said completing the restoration in phases makes the project more economically
feasible for the village and provides more opportunities to seek funding from
federal, state and local sources. The entire project, which consists of nine phases,
carries an estimated price tag of $17 million. Once a natural
resource, by the 1970s, the Pike River was little more than a drainage ditch for
farms. Faced with the challenge of providing adequate storm-water management to
protect properties from increasing flood damage, Mount Pleasant tapped Crispell-Snyder
in 1992 to create an environmentally sensitive design to improve the Pike River
corridor. Initial
plans for improvements to the Pike River stalled in the early 1990s when the state
Department of Natural Resources refused to provide a permit, citing concerns that
the project wasn't environmentally sensitive enough. The DNR approved a revised
plan in 1997 and issued a Chapter 30 permit authorizing the municipality to commence
work along the river.
The first phase of the project increased
the size of the floodway, reduced erosion that degrades aquatic habitat and provided
vegetative buffer strips to filter overland runoff. It also incorporated a public
trail system that connects to other local and regional trails in the area. In
addition, the first phase features four large, environmentally enhanced, flood-storage
areas key elements for decreasing flood flows. "One
area alone provides 240 acre-feet of flood storage," said Weik. The
floodplain storage areas were designed to create a new riparian corridor with
improved biodiversity through the installation of ponds, shallow and deep marshes
and a new meandering base-flow channel.
 |  |
 | |
| Project
Name: Mount Pleasant Storm Water Utility District Pike River Restoration Location:
Mount Pleasant Submitting Company: Crispell-Snyder Inc., Lake Geneva General
Contractor/Construction Manager: C.W. Purpero Inc., Milwaukee Engineer:
Crispell-Snyder Inc. Owner: Village of Mount Pleasant Storm Water Drainage
Utility District Project Cost: $1.3 million Start Date: September
2002 Completion Date: May 2003
|
|  |
 |  |
Weik said that partnerships formed between the municipality
and private businesses, consultants, state and federal regulatory agencies, and
the University of Wisconsin-Milwaukee helped the project continue moving forward. "The
partnership approach was necessary to ensure that not only were engineering needs
met, but also environmental considerations," said Weik. Those
partnerships, which date back to the late 1970s and early 1980s, continue to play
an important role in the design and construction of the overall project. For example,
UWM's Biology Department, which assisted in the preparation of the Pike River
restoration, continues to monitor the river's water quality. Weik said those results
will measure the impact of the restoration, and the final research will become
a model for river restoration throughout the state.
|