|

St.
Joseph Outpatient CenterTeamwork leads to successful outpatient center By
Sean Ryan
The St. Joseph Outpatient Center project is
a story of people and businesses banding together to beat the hourglass. "What
made the project a success was pulling together everyone on the project team,"
said Kristin Ruethling Dufek, architect with Eppstein Uhen Architects Inc., Milwaukee.
"It was really the teamwork that made it a success." During
the planning stages, Covenant Healthcare was forced to trim eight months from
the construction schedule of the $45 million building on Highway 100 in Wauwatosa.
That left general contractor Hunzinger Construction Co., Brookfield, with 10 months
to tear down two hotels and a parking garage and replace them with a 210,000-square-foot
ambulatory care center loaded with high-tech equipment and an 836-stall parking
ramp. Mike
Kelly, chief estimator for subcontractor Olympic Wall Systems, credits Hunzinger
for coordinating the project so that its subs could stay on course.
"There
were a lot of questions, a lot of things that had to be coordinated on a daily
basis," he said. "Everybody had a decent experience there because the
contractor was able to organize." The shortened schedule
meant work began before construction drawings were completed, so Hunzinger and
its team had to juggle a continuous influx of change orders, Kelly said. There
were 62 drawing revisions during the last four months of the project. "They
kept the flow about the job," Kelly said. "At times, there would be
five or six of these construction bulletins for the next day, and then you had
to go back and see what was affected and what had to be changed, and sometimes
things had to be ripped up."
 |  |
 | |
| Project
Name: St. Joseph Outpatient Center Location: Wauwatosa Submitting
Companies: Hunzinger Construction Co., Brookfield; Olympic Wall Systems Inc.,
Brookfield; Eppstein Uhen Architects Inc., Milwaukee General Contractor:
Hunzinger Construction Co. Architect: Eppstein Uhen Architects Inc.
and The BLM Group, Philadelphia Engineer: Arnold and O'Sheridan Inc.,
Brookfield, structural and civil engineer; Harwood Engineering Consultants Ltd.,
Milwaukee, mechanical, electrical and plumbing engineer Owner: Covenant
Healthcare, Milwaukee Project Cost: $45 million Start Date:
July 2002 Completion Date: May 2003
|
|  |
 |  |
The project crew of 700 had to work seven days a week,
on two alternating shifts each day, to wrap things up before the May deadline.
They bolted together more than 1,000 tons of structural steel, poured more than
13,000 cubic yards of concrete and put up 17,440 sheets of drywall, which, if
stacked, would create a 760-ton pile reaching as high as a 78-story building. The
intense construction schedule created a building that was designed to comfort
people. Dufek said that since most people hate to go to hospitals, the design
team tried to create a health-care building that doesn't look like one. That meant
lots of openings for natural light, natural building materials and natural patterns,
such as leaves, on the carpets. "Not only is the technology
in the building new, but it allows patients to stay in a building where they want
to be," Dufek said. "This is a trend that we're seeing more and more
in health care. It's about making health care more friendly."
|