
Milwaukee
Theatre RenovationConstruction team gives Milwaukee Theatre an encoreBy
Rebecca R. Konya When
construction crews began work on the Milwaukee Theatre renovation in the spring
of 2002, it was quickly discovered that the nearly 100-year-old building's wood-pile
foundation system had badly deteriorated.
Replacing the
wooden piles with drilled-steel, concrete-filled piles delayed the construction
schedule by three months. As if the foundation problems weren't bad enough, abatement,
extreme temperatures and difficulty coordinating equipment and manpower required
construction crews to scrap the original 17-month schedule. Working
on a condensed schedule, 62 percent of the project was completed during the final
four months of construction. "We worked two shifts
and weekends," said Michael McNamee, who served as the onsite project executive
for GPD|Gilbane during the renovation. "We had 240 workers on site each day." McNamee
said the November 2003 completion date couldn't be pushed because the Milwaukee
Theatre had already lined up several performances. The
renovation project completely reconfigured the historic Milwaukee Auditorium,
originally built in 1909. Essentially, an entirely new venue was created within
the walls of the existing building in order to provide superior accommodations
for both productions and patrons. The facility continues to serve its historical
uses for convention, corporate and civic assemblies as well as concerts and theatrical
productions.
"We gutted the whole inside," said
McNamee of the renovation project. The former 12,000-seat
amphitheater was converted into the largest and foremost theatrical assembly in
the state. The radical transformation of the main performance
hall created sloped seating in two tiers and a grand, half-domed rotunda lobby.
It also greatly expanded stage, backstage and public circulation spaces. With
seating capacity for 4,100, the Milwaukee Theatre offers excellent sightlines
and superior comfort for audience members. Scott Beglinger
of IBC Engineering Services Inc., which served as project manager for theater
engineering, said the Wisconsin Center District initiated the renovation because
the existing facility couldn't accommodate the type of venues it wanted to host. "They
couldn't use it the way it was," he said.
 |  |
 | |
| Project
Name: Milwaukee Theatre Renovation Location: Milwaukee Submitting
Companies: GPD|Gilbane, Milwaukee, and IBC Engineering Services Inc., Waukesha General
Contractor/Construction Manager: GPD|Gilbane, Grunau/Hunt, Milwaukee Architect:
VOA Associates Inc., Chicago Engineer: IBC Engineering Inc. Owner:
Wisconsin Center District, Milwaukee Project Cost: $41 million Start
Date: May 2002 Completion Date: November 2003
|
|  |
 |  |
The new theater features stunning architecture, including
a new grand entry court set between the existing entry and the U.S. Cellular Arena.
The existing entry was then transformed into a covered garden terrace, accessible
from the main rotunda. Twinkling Tivoli lighting adds a festive atmosphere to
the building's exterior, making every night look like opening night. In
addition to new architectural elements, the public lobby areas were gently reshaped
to enhance the arrival experience of theater patrons, and the back-of-the-house
spaces were expanded to help simplify move-in and technical requirements for staff,
technical personnel and performers. Renovating the interior
of the theater into a completely new venue presented one of the toughest challenges
of the project, said McNamee. He said a tremendous amount of onsite coordination
was needed to ensure safety and productivity at all times.
|