BLUE
SKIES for Blue Harbor
Kraemer sails through resort projectBlue
Harbor Resort & Convention Center and Blue Harbor Condominiums By Candace
Doyle  | | Photo
courtesy of Kraemer Brothers LLC |
Kraemer Brothers
LLC had nothing but high hopes for the Blue Harbor project. They weren't
pie in the sky, either. The massive convention center and condominium project
along Lake Michigan came together like a dream, said Tom Kraemer, president of
the Plain general contracting company. But like most dreams-come-true, the
four-story, 183-suite hotel and conference center took equal parts inspiration
and perspiration. "When you look at a project of this magnitude,"
Kraemer said, "it was just an unbelievable challenge to meet their goal." Kraemer
said his crews had 318 calendar days "from ground breaking to grand
opening" to complete the project, which included a 40,000-square-foot
indoor water park and a 29,000-square-foot conference center. Besides sheer
size, he said the project's challenges included its intricate design. The hotel's
5,000-square-foot, three-story grand lobby and atrium is topped by a dome and
cupola built in place, for instance. Also, the project includes a 120,000-square-foot
condo project 16 Victorian cottages with four units each and a suspended
boat for seating in the Weissgerber's Seabird Restaurant. The water park,
too, is elaborate, with its dueling tube slides and a $1 million interactive lighthouse
water fort.
 |  |
 | |
| Project
Name: Blue Harbor Resort & Convention Center and Blue Harbor Condominiums
Location: Sheboygan
Submitting Company: Kraemer Brothers
LLC, Plain
General Contractor/Construction Manager: Kraemer Brothers
LLC
Architect: ADCI, Lake Delton
Engineer: Pierce
Engineers Inc., Milwaukee
Owner: The Great Lakes Companies Inc.,
Madison
Project Cost: $41.5 million
Start Date: July
2003
Completion Date: June 2004 |
|  |
 |  |
While Kraemer's familiar with the hospitality market, he said working
with Geofoam, a material used in place of fill in some areas because of inadequate
soil conditions, was new, as was working with water-park equipment manufacturers. "That
adds a new dimension to the project," he said. ut the tight time line
was met, largely because the team of contractors assembled was committed to the
project. Kraemer said a commitment was made to work with local construction firms,
resulting in $11 million in contracts. "Contractors have a habit of
bringing their buddies along when they're not in their area," said Kraemer,
adding that the company purposely associated itself with local firms that "wanted
to create the same conclusion." One such local contract required thousands
of wall panels to be assembled off site, shipped to the job and lifted into place.
Trailers were delivering dozens of walls to the site each day 4,050 used
in the hotel alone. At one point, Kraemer Brothers had three crews, four cranes
and 15 man-lifts going at once installing walls and roof and joint trusses. On
average, there were 250 workers on site each day, with about 90 Kraemer Brothers
people there at times. That created a sense of camaraderie that "helped the
construction goal." "Frankly, it worked out very well in that
regard," he said. |