| ROOM
to Move
Biotech addition team tackles a tight spotUniversity
of Wisconsin-Madison Biotechnology Center Addition  | | Photo
courtesy of Miron Construction Co. Inc. |
Construction
of the University of Wisconsin-Madison Biotechnology Center addition truly tested
the creative reflexes of all the firms involved. The project was pinched
into a tight spot that offered only 20 to 30 feet of room on three sides of the
building and a busy Madison street on the fourth side. With so little space around
the structure, there was no room to store materials or trucks at the site. That
forced the project team to precisely schedule deliveries and pour concrete between
midnight and 6 a.m. "Trucks had to get in and get out," said Russ
Owens, project manager from Miron Construction Co. Inc. But space constraints
weren't the only challenges on the job. Due to height restrictions on the structure,
the air handlers, typically placed on the roof of a building, had to be inside.
As a result, the first floor of the building is about 80 percent mechanical space,
Owens said. Custom-designed air handlers were delivered in pieces and put together
inside the facility. Once assembled, they are larger than a train car, Owens added. "We
never did a project quite like this," he said. Construction of an animal
research facility in the lower level presented other challenges to the architects
and contractors. Creating a space that could house the complex equipment and offer
the proper maintenance of air quality was not easy. Even with all the quirks
of this unusual project, crews managed to finish 17 days early and with no lost-time
injuries.
 |  |
 | |
| Project
Name: University of Wisconsin-Madison Biotechnology Center Addition
Location:
Madison
Submitting Companies: Miron Construction Co. Inc., Neenah,
and Potter Lawson Inc., Madison
General Contractor: Miron Construction
Co. Inc.
Architect: Potter Lawson Inc.
Engineers:
Affiliated Engineers Inc., Madison, mechanical, electrical and fire protection
engineer; SRI Design, Madison, structural engineer; GPR Planners, Purchase, N.Y.,
laboratory engineer
Owner: State of Wisconsin
Project
Cost: $23 million
Start Date: December 2002
Completion
Date: August 2004 | |
 |  |
 | The
$23 million, five-story, 95,600-square-foot facility certainly was a challenge
to build, but it provides sorely needed space for the Genome Center and Laboratory
of Genetics, both of which had been housed in the university's old Genetics Building.
The new structure contains research laboratories, laboratory support, faculty
offices, an animal research facility and workstations for research support and
staff. Eric Lawson of project architect Potter Lawson Inc. said the space
was designed to be extremely flexible, which will allow the university to mod-ify
its laboratories as research needs change over the years. A dry lab, for example,
can easily transform into a wet lab if required. From the start, the incorporation
of natural daylight into as many areas as possible was a goal, Lawson said. "The
corridors, all the labs have access to natural daylight," he said. "The
workstation areas do, too." Owens said his crews, along with every
other firm involved in the project, learned a lot in building this structure. A
schedule that was constantly updated and fine-tuned allowed a lot of work to get
done in less than 600 days, and employees at the lab can now enjoy this state-of-the-art
facility. For some of those who worked on it, the project, despite its
high-tech nature, brought to mind an old-school building technique not seen much
today. "It was like building a battleship in a bottle," Owens
said. |