A
SOARING Success
C.D. Smith flies through airport projectAustin
Straubel International Airport Concourse BBy Brendan O'Brien  | | Photo
courtesy of C.D. Smith Construction Inc. |
Imagine
rushing through a crowded airport. Now imagine constructing a 45,000-square-foot
concourse in the same crowded airport. That's what C.D. Smith Construction
Inc. accomplished when the Fond du Lac contractor completed construction of Concourse
B at Austin Straubel International Airport in Green Bay. "We have
done work in airports in the past but nothing like this, where we have to actually
cross the path of planes," said Greg Sabel, C.D. Smith's project manager. "We
are used to dealing with vehicle and pedestrian traffic, but 747s is certainly
a new element." The contractor also had to deal with security provisions
that kept construction workers from freely moving in and out of the site. C.D.
Smith kept to a defined hauling route painted on the pavement and followed strict
security measures. "A gate guard
inspected trucks and talked
to [workers] and then radioed some of the personnel on the site," Sabel said.
"We had to visually be able to see that truck leave the gate and come into
the site." The guard, site superintendent and control tower communicated
by radio and directed traffic. "Once it got going, you knew the patterns
of the flights," Sabel said. "We constantly would be sweeping the concrete
because if any rock or anything falls off these trucks, jets can suck it right
up. The amount of time to make sure that people got out there safely and the area
was clean was unbelievable." The result of the coordination is a stately
airport concourse with six boarding gates, a members' lounge and a children's
area. The interior features a porcelain tile floor, 20-foot ceilings and nine
illuminating skylights.
 |  |
 | |
| Project
Name: Austin Straubel International Airport Concourse B
Location:
Green Bay
Submitting Company: C.D. Smith Construction Inc., Fond
du Lac
General Contractor: C.D. Smith Construction Inc.
Architect:
Mead & Hunt, Madison
Engineer: Mead & Hunt
Owner:
Brown County
Project Cost: $9.2 million
Start Date:
May 2003
Completion Date: September 2004 |
|  |
 |  |
"It was just a neat project because we got to do stuff that you
don't typically get to do," Sabel said. "With the high ceilings and
the ceramic, they are really trying to impress people coming in. It is fun to
do a building where it's that kind of wow factor when you walk in." C.D.
Smith constructed the exterior of the concourse with large metal panels and massive
glass curtain walls. Each section needed to be precisely measured before the contractor
placed the material order. "It had to be field measured," Sabel
said. "There were too many ins and outs to take a gamble on those panels.
They are expensive items. There was a lot of coordination on the outside, but
it turned out perfect." The design of the concourse involved many corners
and angles. "There are not many straight lines," Sabel said.
"That was probably the most difficult thing about the layout. You were just
turning 30 feet here, and then you are taking a 90-degree angle. Everything was
in, out, in, out." The concourse sits on new, 2-foot thick concrete,
and the specifications for that portion of the project were extremely rigid, he
said. "We were pouring 300 to 500 yards a day for a month and a half,"
Sabel said. "That was an incredibly intense project." |