|

Boson clears the field for readiness center
 |
The
Boson Co. Inc.’s construction crew puts a brick veneer on the higher
areas of the building before the cold weather sets in.
Photos courtesy of The Boson Co. Inc. |
The construction site looked perfect at first glance.
The nice, big lawn at Camp Williams near Camp Douglas practically begged
The Boson Co. Inc.s construction team to build the Camp Douglas
Readiness Center for the Wisconsin Army National Guard. To the naked eye,
the site looked ready for building in July, especially after Boson removed
three barracks from the general area.
But the eye, naked or otherwise, couldnt grasp the troubles lurking
below that innocent-looking patch of grass.
There was stuff going everywhere under this site, said Joe
Dolezal, project manager, director of construction services and safety
director for Boson. The reason there were no buildings in the past
is there is a maze of underground, private utilities infrastructure. There
was gas, power, water, sanitary and storm water.
The building had to fit within that.
Dealing with underground utilities isnt an unusual challenge for
contractors. They call in Diggers Hotline, get the various lines tagged,
make the necessary reroutes and start digging.
The services belong to the military, so we couldnt call Diggers
Hotline, Dolezal said. I think most contractors would go,
Wow, that couldnt have been fun.
If Diggers Hotline makes a mistake, its not our responsibility.
Here, there was no Diggers Hotline to go back to.
 |
| The
construction team places structural-steel joists on the Camp Douglas
Readiness Center. |
So Boson did the next best thing. It brought in people from the Department
of Military Affairs to help find the utilities, and the contractor hired
a private locator to assist.
We knew if we missed something, wed have major problems,
Dolezal said. We spent almost a month just doing that.
We did so much planning, verifying, checking and rechecking that
I personally felt we werent going to hit anything. It was a major
struggle, but it went off without a hitch.
And finally, in August, Boson set about constructing the single-story,
47,000-square-foot, military training center. The structure will accommodate
300 men and women and features a classroom auditorium, kitchen, vehicle
maintenance bay, large assembly hall, a concrete-reinforced arms vault,
regular classrooms and offices.
And as the job heads into December, the project is right on schedule,
thanks, in part, to the teams early prep work during a lull between
the bid award in April and the contract award in July while the state
generated more funds for the job. The roof is on, the brick veneer is
partially installed, window installations are under way, the heating equipment
is on site, and the mechanical rough-ins are rolling.
There is not another place like this in the state right now,
Dolezal said. Its the headquarters for the 32nd Infantry Brigade.
Its something the Army National Guard is very excited to have, and
theyre going to be very proud of it.
- Chris Thompson
Project Essentials
Project Name: Camp Douglas Readiness Center
Location: Camp Douglas
Owner: Wisconsin Department of State Facilities
General Contractor: The Boson Co. Inc., Marshfield
Architect: Fischer-Fischer-Theis Inc., Waukesha
Estimated Project Cost: $7.6 million
Start Date: July 2006
Scheduled Completion: July 2007
Project fact
Every worker on the job submitted to a background check. On the full
project, there were close to 500 people who had to be cleared.
|