| |

Riley
acts fast for TCF Bank | A
Riley construction crew works on the glass-enclosed vestibule entrance for TCF
Bank's Oak Creek branch.
Photos courtesy of Riley Construction Co. Inc. |
The
grand-opening date never changed. TCF Bank had Jan. 1 in mind when Riley
Construction Co. Inc. took the job to build the banks Oak Creek branch.
It remained Jan. 1 even after Riley watched the first two months of its schedule
evaporate in a cloud of contaminated soil. All the plans were turned
over, we had the permits, and we were ready to rock n roll on July
1, said Ben Kossow, Rileys project manager. Riley, which negotiated
for the job after completing a similar project for TCF in West Milwaukee, might
have been ready, but the property wasnt. TCF bought the Oak Creek land from
a developer with an agreement that the devel-oper would set up a retaining wall
to separate the construction site from a retention pond, Kossow said. But
the developer found contaminated soil when it started its work, and it took two
months to get the property ready for Riley, Kossow said. But the bank,
per their quotas or goals, asked the ever-so-famous question, Can you still
get it done by the end of the year? he said. And, like all contractors,
we said, Why yes, we can get it done by the end of the year.  | A
Riley mason puts the finishing touches on TCF Bank's drive-through window in Oak
Creek.
Photos courtesy of Riley Construction Co. Inc. |
So
when Riley finally got on the site in the first week of September, it still faced
building a 4,580-square-foot, one-story bank with an atrium, offices, teller stations
and a drive-through. But the contractor had two less months to do it. It
hasnt been a problem because, Kossow said, the project team used those two
down months to prepare rather than panic. In July and August, we were
preordering steel, millwork, doors and ceramic tile, so when they said go, we
could go, he said. With everything we learned on the last bank, we
used it to our advantage. And in the time since Riley got on the site,
the contractor did more than just catch up. In October, the team was running two
weeks ahead of schedule and planning to reach the finishing stages by the end
of November. Kossow, meanwhile, said hes happy with the progress and
doing everything he can not to jinx such a smooth project. I was at
a meeting, and I said that things couldnt be going any better, and before
I could finish, they told me to stop, he said. Everybody is ecstatic
about how its going. I was nervous, but I knew in my heart we could get
it done. Chris Thompson Project
Specs Project Name: TCF Bank Oak Creek Branch Location:
Oak Creek General Contractor: Riley Construction Co. Inc., Kenosha Architect:
Integrated Building Solutions Inc., Cottage Grove Estimated Construction
Cost: $1.4 million Start Date: September 2005 Scheduled Completion:
December 2005 Project Fact After finding
contaminated soil on TCF's Oak Creek site, the developer removed nearly three
quarters of the site 10 feet deep. Fixing the problem required 10,000 cubic yards
of limestone byproduct going in and about 600 truckloads of contaminated soil
going out.
|
|
|