Consolidated waits its turn for hotel job
 |
Consolidated
Construction crews finish pouring the foundation for the north wall
of the 55,209-square-foot hotel in Mole Lake.
Photos courtesy of Consolidated Construction Co. Inc. |
The house went down on Dec. 5.
In the weeks leading up to its demolition, it stood as a solitary protest
to the project. The home owner, a tribal member of the Mole Lake Sokaogon
Chippewa Community, refused to leave despite offers for new lodging and
a tribal ruling mandating that he step aside.
And as long as he stayed, the Consolidated Construction team charged
with building the Mole Lake Hotel and Conference Center in Mole Lake was
stuck.
The house sat on the footprint of the 65,631-square-foot, three-story
project. That kept Consolidated from finishing the foundation, which,
in turn, left the framing team waiting in the wings. The power poles running
lines to the house blocked the team from putting in the elevator shaft.
So Consolidated waited and watched as its construction pace slipped behind
schedule by three to five weeks.
Normally in the course of a project, you reach obstacles and move
through with rational decisions, said Mark Schwei, Consolidateds
executive vice president. This is emotional. Were talking
about a person, and you just dont navigate that.
 |
Crews
install a 6-inch water main for the Mole Lake Hotel and Conference
Center.
Photos courtesy of Consolidated Construction Co. Inc. |
But the contractor finally found clear sailing when the home owner relinquished
his hold, and now the project is all about catching up.
Well continue on with construction and work with the owner,
Schwei said. We will do our best to make up the schedule in other
areas as the project proceeds. But there are no guarantees.
The goal of the project, though, remains firm. The conference center
and 75-room hotel, which is attached to the tribes casino, will
feature a meeting area, bar and aquatic center complete with a childrens
pool.
They are trying to create a destination resort, Schwei said.
And Consolidateds commitment to go above and beyond the typical
requirements of a general contractor is also as solid as it was when the
project got rolling at the end of October, he said.
Were building it, contracting the operating company on behalf
of the tribe, doing the interior decorating and supplying the furniture,
fixtures and operating systems, Schwei said. Were changing
their lives, and we have the expertise within our construction company
to develop the whole project beyond construction. And oh, by the way,
well build it too.
And no matter what obstacles stand in the way of completion, Schwei said
hes confident the American Indian tribe will be happy with the result.
The excitement level of the local people is just phenomenal,
he said. From a marketing point of view, theyre looking for
more economic vitality.
Chris Thompson
|
Project Fact
The construction agreement for the project makes
provisions for enforcement in the county and circuit court systems
rather than in the tribal nation.
Project Essentials
Project Name: The Mole Lake Hotel and Conference
Center
Location: Mole Lake
Owner: Mole Lake Sokaogon Chippewa Community
General Contractor: Consolidated Construction Co. Inc., Appleton
Architect: Design II Architects, Fond du Lac
Estimated Project Cost: $7.5 million
Start Date: November 2006
Scheduled Completion: June 2007
|
|