Northern
Wisconsin Regional Council of Carpenters Training Facility
Basic Training
Carpenters'
facility focuses on materials
By Jennifer Pfaff
Two massive columns stand sentinel outside the Carpenters union training
facility in Madison.
They offer an early introduction to the buildings
central theme, which focuses on the materials that carpenters use and the creative
ways they use them.
Those columns, flanking the entry to the Northern Wisconsin
Regional Council of Carpenters Training Facility, are wrapped with 24-inch-diameter
logs that were trucked in from northern Wisconsin, said Jeremy Cortesio, project
manager for general contractor KBS Construction Inc. of McFarland.
Those
didnt come from the site, he said. If we had thought of it sooner,
they probably would have.
The 27,000-square-foot building contains
office space, classrooms and a hands-on training area. Its design and construction
sought to showcase the construction possibilities that carpenters can take advantage
of while they remain sensitive to the environment, Cortesio said.
For example,
the crews on the project recycled as much building material as possible, including
the trees felled to make room for the training center.
The owner
had 25 to 30 trees, if not more, set aside, Cortesio said. We had
to clear out some trees to make way for the building. He had some of the logs
kiln-dried and sawed up for use as base and casing material on the building.
We
ended up trying to change some of the other wood in the building, for instance
the doors, to match the trees we were getting from outside.
Project
Name: Northern Wisconsin Regional Council of Carpenters Training Facility
Location:
Madison
Submitting Company: KBS Construction Inc., McFarland
Engineers: Arnold & O'Sheridan Inc.,
Madison, structural, electrical, mechanical, HVAC, plumbing engineer; Schreiber/
Anderson Associates Inc., Madison, civil engineer
Owner: Northern
Wisconsin Regional Council of Carpenters, Kaukauna
Project Cost:
$3 million
Project Size: 27,000 square feet
Start Date:
December 2004
Completion Date: September 2005
But the log columns at the facilitys entry required a more time-consuming
preparation.
Usually, you are kiln-drying sawn lumber, but in the
case of the entryway, they have to kiln-dry an entire log, so it only dries out
so far into the log, Cortesio said. You have to let it sit for months
so the rest of the log can dry, and you wont get much checking.
The
project designers and the Carpenters union wanted to show the full range of materials
not just the woodwork involved in the trade.
That presented
some construction challenges, Cortesio said. The three separate areas of the building
were each made from different material combinations.
The 25-foot-high shop,
which offers enough space to build and tear down a house, is made of basic precast
concrete with a steel structure and rubber membrane roof.
The classroom
section is constructed partially from structural steel and partially from light-gauge
steel stud frame with a metal seam roof.
In the office setting, glue-laminated
beams were used for the columns and beam structure, and KBS switched to wood studs.
A rubber membrane roof again was used. Exterior materials also varied. Precast
concrete panels, zinc metal wall panels and cedar siding all played a part.
What
that created, it was almost like building three separate buildings, Cortesio
said. As you went from one section to the other, you would start over with
trying to procure new materials and figuring out all of the connection details.
When you start a certain structure, your efficiency comes several
weeks in. Just as we were getting efficient with the structure, we were starting
over again.