It seems everything happens in threes at the Dane County Courthouse in
Madison.
There are three entrances, three hallways, three sets of elevators
and three staircases. There are essentially three distinct ways to travel the
building, although few people will ever experience all of them, said Jerry Olson,
managing principal of Durrant Group Inc., Hartland.
There needed to
be a separation of circulation, he said. There are three groups of
people who use the building and need to be kept separate.
The first
is the secure inmates; they cannot cross any other circulation path. The second
is the judges and courthouse staff, and the third is the public. The reason for
that separation is the safety of the patrons.
In addition, giving
judges, bailiffs and other staff their own entrance, parking area and means of
traveling throughout the building reduces the risk that jurors or others involved
in cases will overhear or see information that might affect an ongoing trial,
Olson said.
All of the judges and staff who support the records are
behind the courtrooms, he said. All of the public activity is in front
of the courtrooms.
Inmates brought into the building are guided through
a secure vertical path. Elevators and doors in the courthouse can be controlled
from a nearby safety center.
Cameras, along with a variety of other safety
features, help bailiffs keep track of inmates, Olson said.
It was this need
for modern safety features that drove the construction of the $31.2 million, 10-story
justice center, which is adjacent to Madisons Public Safety Building.
The
center was built using sustainable concepts, including fixtures and furniture
from the former courthouse and products made from recycled materials. It houses
20 courtrooms and two rooms that can be converted for courtroom use in the future.
It also features a café, law library, media room, jury assembly room, juvenile
court and administrative spaces.
Project
Name: Dane County Courthouse
Location: Madison
Submitting
Company: Durrant Group Inc., Hartland
General Contractor: Miron
Construction Co. Inc., Neenah
Architect: Durrant Group Inc.
Engineer:
Durrant Group Inc.
Owner: Dane County
Project Cost:
$31.2 million
Project Size: 257,039 square feet
Start
Date: April 2003
Completion Date: December 2005
The need for separate circulation paths presented a variety of design
challenges for a project with limited land availability, Olson said. And the lack
of land presented the greatest challenge of all.
The site, the site,
the site, he said. The site [Dane County] gave us originally and the
program didnt match.
The original plan called for a 250,000-square-foot
building, and the site could only accommodate about 150,000 square feet. So the
county executive and a design committee developed a new plan requiring about 216,000
square feet still too much building for the designated location behind
the Public Safety Building.
The county eventually purchased additional land
and tore down two office buildings to make room for the courthouse. Even then,
the space available was triangular and difficult to work on, Olson said.
The
building sits atop an extreme slope, with the front corner about two floors above
the nearby intersection. It made pouring footings difficult and left almost no
room for staging.
So the project team used the nearby Dane County Coliseum
to store equipment, which had to be driven over every day before morning rush
hour, Olson said.
The difficult site also affected materials decisions.
We
took a look at masonry and the scaffolding that would need to go up eight stories,
Olson said. That was difficult to look at and led to looking at precast
concrete.
The result is a modern courthouse that defies some of the
tradition of justice facilities.
Theres a history of courthouse
design that goes back to our ancestors, Olson said. Theres a
feeling a courthouse should have columns and an entry processional.
We tried
to take that on as much as we could, but the design had to be in todays
nomenclature.