State
of Wisconsin Department of Natural Resources Northeast Regional Headquarters and
Service Center
Taking the Leed
DNR project hits milestone for
state
By Holly Johnson
Neil Diamond would be proud.
It might seem unusual, but the project
team for the state Department of Natural Resources Northeast Regional Headquarters
and Service Center took the famous singer at his word when designing the project
in Howard. It truly will be forever in blue jeans.
Recycled blue jeans,
as it turns out, make for good sound insulation. And thats just the sort
of unexpected material Oscar J. Boldt Constructions team used in achieving
silver level certification for the project from the U.S. Green Building Councils
Leadership in Energy and Environmental Design program.
Its the
first state building with the LEED certification, said Dave Shoemaker, Boldts
project manager on the job.
The job included two buildings a cold
storage/service facility and the DNR office headquarters. At more than 34,000
square feet, the three-story office building provides space for 156 employees
and lets the DNR combine staff from four different locations in the Green Bay
area.
Its on the side of a natural slope in the middle of a 16-acre
lot dominated by a marsh, a creek and other wetlands. That location actually helped
the project team reach its green-building and LEED goals, Shoemaker said.
Project
Name: State of Wisconsin Department of Natural Resources Northeast Regional
Headquarters and Service Center
Location: Howard
Submitting
Company: The Boldt Company, Appleton
General Contractor: Oscar
J. Boldt Construction, Appleton
Architect: Berners-Schober Associates
Inc., Green Bay
Owner: State of Wisconsin
Project Cost:
$5.2 million
Project Size: 48,395 square feet
Start Date:
October 2003
Completion Date: April 2005
Part of the LEED process calls for as much interior sunlight as possible,
and constructing on a slope let the team expose the buildings lower half
on the north side. That side of the building is covered with windows, allowing
the DNR to use the basement for office space.
It doesnt hurt
that, in my opinion, they have a pretty nice view, Shoemaker said. But
the main purpose is to bring natural light into the work space. Ninety-eight percent
of the work spaces have natural daylight.
The project also achieved
some nice percentages when it came to recycling. The team recycled 86 percent
of the material from the job and easily outpaced the minimum requirements for
LEED certification.
Its a credit to the people on the site,
Shoemaker said. Certainly, training had to be done. Once that was done,
things fell into place pretty favorably.
And the green approach continued
all the way down to the selection of materials with low levels of volatile organic
compounds. VOCs in materials such as carpet, glues and other adhesives have a
tendency to release gasses as they cure, and that can lead to sick employees,
Shoemaker said.
Its not just a nice thing to do, he said.
Youre creating an environment where employees are happier, more productive
and healthier. All those things play into a successful building.
But
a successful LEED-certified building requires even more. The project team paid
close attention to documentation, which turned out to be a daunting task.
The
biggest challenge was to coordinate with all the suppliers and subcontractors,
Shoemaker said. Everyone had to communicate and document a lot. Its
a very collaborative effort between architects and engineers, and the owner has
to be willing also.
The documentation process also included a third-party
monitor to make sure the project team used the right materials for LEED certification
and installed everything correctly.
The state hired an independent
commissioning agent and had a very stringent commissioning plan that had to be
followed, Shoemaker said. Typically, at the end of the project, somebody
does the testing. But by getting on board early, they were able to monitor the
entire construction process.
And if the requirements for LEED certification
werent enough, the team also had to overcome the challenges presented by
Wisconsins weather, Shoemaker said.
We started in December 2003
a very difficult winter, he said. Its always tough to
start building in December in Wisconsin.