University
of Wisconsin Hospital & Clinics Rooftop Heliport Facility
On the Fly
Findorff
meets its heliport deadline
By Janine Anderson
Emergency situations require quick decisions and no mistakes.
Thats
how personnel at the University of Wisconsin Hospital & Clinics react every
time a patient arrives on a helicopter. Thats how J.H. Findorff & Son
reacted as the deadline approached for a new helicopter landing pad on top of
the Madison facility.
And when UW Hospital held its grand opening for the
new facility, Findorff made sure there was a completed project to celebrate.
This
was a big, marquis project, said Mark Premo, Findorffs project manager.
There was a lot of pressure to get that done on time. It was really exciting
and a different type of project. I dont think youll find a heliport
like this in the state.
The complicated project gave the hospital
the necessary roof space to land two helicopters and the facilities needed to
fuel and maintain them. UW Hospital needed the project so it could operate its
rescue-helicopter service more efficiently.
Instead of taking helicopters
somewhere else for fueling and maintenance, the hospital can now perform that
work on-site, cutting down the time it takes to get patients transported to and
from the hospital in emergency situations.
But building the landing pad
wasnt easy.
This is a vertical expansion, and it was directly
in the middle of the hospital, Premo said. You couldnt have
picked a more difficult location to get to.
This was where it made
the most sense for it to be. It had the most open sight lines as far as a pilot
coming in. But as far as the building, it made it very difficult to get there.
Findorff
started by chipping through the existing roof to get to the steel supports. The
seven-floor hospital has 18-foot floors, putting the project team the equivalent
of about 10 stories up.
Project
Name: University of Wisconsin Hospital & Clinics Rooftop Heliport Facility
Location:
Madison
Submitting Company: J.H. Findorff & Son Inc., Madison
Construction
Manager: J.H. Findorff & Son Inc.
Architect: HGA Architects
and Engineers Inc., Milwaukee
Engineer: HGA Architects and Engineers
Inc.
Owner: University of Wisconsin Hospital & Clinics Authority,
Madison
Project Cost: $8.9 million
Project Size: 46,000
square feet
Start Date: February 2005
Completion Date:
November 2005
On top of that, the hospital stayed open throughout the process.
The
floor below us was patient rooms, Premo said. They had existing services
that had to remain in place until the new mechanicals were available to change
them out. There had to be careful coordination between mechanical, electrical
and ourselves in how we built this.
We had 16 of these shutdowns
that affected critical-care areas. It had to run very smoothly. We had to have
it go like clockwork.
Simply getting materials to the site was a challenge,
he said. Findorff put a tower crane on top of an empty elevator shaft, and all
materials came up through that crane. It was the only way to get to the roof.
There
was no lay-down area around the hospital, Premo said. We brought material
in right next to the emergency room. The emergency entrance is barely two lanes.
We had to be in complete contact with dispatch downstairs so if
there was an ambulance coming in, we had to clear the way. That takes precedence
over getting material on the site.
While the new landing pads were
being built, the hospital was still using its existing helicopter facility. So
each time a helicopter arrived, the tower crane moved out of the way.
Every
time it came in, wed have to turn a certain way so it wouldnt impede
where they were landing, Premo said.
The challenges the site presented
made the work difficult, but Findorff came through and completed the project just
in time.
We cut it close, Premo said. We got our occupancy,
and just the day before we were ready to go, we had our final walk-through by
the state. We had a nice grand opening.