
Site
for 601 Lofts cleans up well | 601
Lofts gets a post-tension concrete deck on level one.
Photos courtesy of
Beyer Construction |
A building is only as good as
the ground beneath it. And no building will sit well on ground filled with
buried foundations, buried tanks, foundry sand and a variety of other discarded
or forgotten materials. Those are basic facts that Beyer Construction confronted
early in the process of building 601 Lofts on East Ogden Avenue in Milwaukees
East Pointe neighborhood. When complete, the 10-story, mixed-use structure
will feature 8,500 square feet of commercial and retail space on the ground floor
and 79 residential units ranging from 950 square feet to nearly 3,800 square
feet on floors three through 10. Plans also include parking in an underground
level and on the second floor. But before Beyer could worry about the finished
product, it had to deal with the site. I guess Ill always remember
the soils, said Tom Smith, Beyers vice president and director of construction.
As we started excavation for the foundation, we ran into everything on the
site. From day one, we were dealing with the soil issue, and thats the biggest
challenge so far. It was a challenge that Beyer and project developer
KeyBridge Group Inc., Waukesha, tackled shortly after construction began in August.
Working with the state Department of Natural Resources, the project team got the
site cleaned up and began a steady climb to the top of the building. Theres
nothing that time and money dont take care of, said Scott Fergus,
president of KeyBridge. The underground work has the biggest potential for
surprise. To remedy it is actually very predictable, and it was generally very
good working with the DNR.  | The
columns on level two of 601 Lofts are formed and ready to support the third-floor
deck.
Photos courtesy of Beyer Construction |
Cold
weather threw another challenge at Beyer as the contractor spent the winter laying
the foundation and building the concrete walls for the first two floors. But as
the project heads toward May, Smith said the skeleton of the building should be
nearing completion with work focusing on the third levels exterior metal
studs and the lower levels mechanical systems. I think, overall,
Im pleased, he said. I wish we were further ahead of schedule,
but progress will accelerate. Were looking forward to spring. Fergus
said hes happy with the schedule and anticipating a completed project that
will add a twist to the traditional designs of similar residential buildings.
601 Lofts, he said, will feature varied roof lines and two corners made entirely
of glass. After we made it through the delays, progress has been very
good, and its timed out well for us in the market, he said. Its
going to be a building that will change the landscape of the East Pointe neighborhood. The
key to construction is making sure the design works. It does. -
Chris Thompson Project
Specs Project Name: 601 Lofts Location: Milwaukee Developer: KeyBridge
Group Inc., Waukesha General Contractor: Beyer Construction, New Berlin Architect:
Eppstein Uhen Architects Inc., Milwaukee Start Date: August 2005 Scheduled
Completion: January 2007 Project Fact The design for 601 Lofts
calls for two levels of parking to make sure there’s a parking spot for every
bedroom in the development. |
Copyright
© 2006 The Daily Reporter Publishing Co. |