|
|
Science underground
Excavation work stands out at UW research building
|
You need to upgrade your Flash Player
This is replaced by the Flash content. Place your alternate content
here and users without the Flash plugin or with Javascript turned
off will see this. Content here allows you to leave out noscript
tags.
|
Work inside the University of Wisconsin-Madison Microbial Science Building
is being done at a high level. But the work done to build the foundation
underneath the building is top-notch as well.
Excavation for the 390,000-square-foot building required digging down
60 feet in some areas, such as directly in front of UW-Madisons
historic Hiram Smith Hall, a building that dates back to the late 1800s,
said Gerry Wheaton, project manager for C.D. Smith Construction, the projects
lead contractor.
Just getting the building up out of the ground was a challenge
in and of itself, Wheaton said.
The sloping site had more than 20 feet of elevation change, according
to Plunkett Raysich Architects, which worked extensively on the project.
There were no other options other than to use some form of earth
retention, Wheaton said. The building was large, and the area
of the project was small, so we were going right up tight against the
roads in some places.
The projects contractors used several forms of earth retention,
Wheaton said, including shotcrete and soil nails to hold the sites
walls securely in place and H-piles with lagging.
Wheaton said poor soil in one area of the site also was an issue, as
was working around a substation power plant in the basement of an existing
building that had to remain in place and operational throughout.
That was a real challenge, said Arden Parfitt, project manager
for Town & Country Electric. We had to build right around it,
which was very different.
|
Project Essentials
Project
name: University of Wisconsin-Madison Microbial Science Building
Location: Madison
Submitting companies: C.D. Smith Construction., Fond du Lac; Plunkett
Raysich Architects, Milwaukee; Town & Country Electric, a division
of Faith Technologies Inc., Sun Prairie
General contractor: C.D. Smith Construction
Architect: Plunkett Raysich Architects
Engineers: Arnold & OSheridan Inc., Madison, structural;
PSJ Engineering, Madison, plumbing and fire protection; Ring &
DuChateau Inc., Milwaukee, mechanical
Owner: Wisconsin Department of Administration, Madison
Project size: 390,000 square feet
Project cost: $120 million
Start date: January 2005
Completion date: July 2007
|
The substation powers more than one-third of the UW campus, said Scott
Kramer, a partner with Plunkett Raysich.
Designing around the electrical substation posed a number of different
challenges, Kramer said. The substations location also
played a part in the design and structural considerations of the building.
The buildings contractors also were careful to work around a very
old, large, white oak tree in the corner of the site that could not be
disturbed.
It was truly a complex project, said Ben Menaker, assistant
project manager for C.D. Smith.
The building includes a 450-seat symposium for hosting local and international
seminars, two large classrooms, a discovery center for people of all ages,
a four-level underground parking garage and research labs.
The building is one of the largest and most costly buildings on
the UW-Madison campus, Kramer said. It is an impressive structure,
being the first multidisciplined research facility of its kind.
Caley Meals
` |