|

Ellis Stone meets challenges of Dovorany job
 |
The
Dovorany Professional Building's concrete block foundations, structural
steel and precast concrete floor planks are in place.
Photos courtesy of Ellis Stone Construction Co. Inc. |
The lease is up at the end of December.
It wasnt supposed to be that way. Ellis Stone Construction Co.
expected its construction schedule to run to the end of January.
But, in all likelihood, John Dovoranys landlord didnt have
Ellis Stones construction time line at the top of the priority list.
And if Dovorany needs to leave his rented space earlier than expected,
then Ellis Stone has to similarly adjust its plans to finish Dovoranys
new orthodontic offices.
Its that simple. Yet, its not simple at all.
We had to shorten our existing schedule by three weeks, said
Jay Johnson, architect with Ellis Stone. Were looking at double
shifts or overtime.
And even with the extra work, theres a solid chance Ellis Stone
will still be finishing the 10,646-square-foot, two-story office building
when Dovorany moves in.
We cant have any slip-ups with critical materials not being
delivered on time, said Jim Anderson, president of Ellis Stone.
Everything has to start and complete on time.
 |
| Masons
lay the brick veneer in a bed-side-out coursing pattern. |
It wont be easy for the Stevens Point contractor, but, really,
easy isnt a common word on the Wausau job site anyway. It wasnt
easy designing the building to fit on a steep slope, and the word certainly
didnt apply to the water-drainage issues or the fact that the Wisconsin
Department of Transportation has plans to lower the road fronting the
project.
But Ellis Stone is taking each challenge in stride. The contractor pumped
out and diverted the settled water and turned the slope into a positive
by creating grade-level entrances on both the first and second floors.
As flexible as Ellis Stone managed to be with the project, the plans
by WisDOT still threw a curve at the design/build contractor. The company
was in the midst of planning construction on the 1-acre site when WisDOT
stepped in, removing usable land from the site and placing easements on
other areas.
We had to keep that in mind and not put the building in the easement,
Johnson said. It was a pain not knowing that up front because we
started the design work.
But the contractor is persevering, and, as the project moves through
its halfway point in October, the structure should be totally enclosed
with mechanical and electrical rough-in work beginning.
And despite the scheduling and construction issues, Johnson said the
job is a success.
Things have gone very smoothly so far, and I think its because
of good communication between the owner, myself and the superintendent,
he said. Its a unique challenge, but, then, every project
is.
- Chris Thompson
Project Essentials
Project Name: Dr. Dovorany Professional Building
Location: Wausau
Owner: John Dovorany
Design/Build Contractor: Ellis Stone Construction Co., Stevens
Point
Estimated Project Cost: $1.5 million
Start Date: July 2006
Scheduled Completion: Jan. 1, 2007
Project Fact
The brick for the Dovorany building is laid bed-side-out,
which means the normal horizontal surface that each course of brick is
set on is laid vertically so the bed face acts as the veneer of the building.
|