|

Janke takes the safest path
 |
Janke
General Contractors is taking a cautious approach in creating a new
bike path for the University of Wisconsin-Madison.
Photo courtesy of Janke General Contractors Inc. |
It sounds simple.
Janke General Contractors Inc., Athens, is building a 4,100-foot bike
path on the west end of the University of Wisconsin-Madison campus. The
path will run parallel to Campus Drive from University Bay Drive to about
1,600 feet beyond Walnut Street.
Thats pretty much where the easy part of the job ends.
Its a slow-going project, said Steve Janke, president
and owner of Janke General Contractors. Throw down gravel and blacktop
it aint that type of project.
The jobs complications start with a plan to build a bridge over
Walnut Street for the path. That structure will sit next to the railroad
bridge over the street.
Janke said building bridges is a standard job for his company, but its
not every project that requires a company to excavate for bridge abutments
and drive piles around a buried high-voltage power line.
We were told that if you hit that, youre going to evaporate,
he said. Theres also a high-pressure gas line buried there.
That high-pressure gas would probably put a crater in the ground.
Theres a lot of hand shoveling, needless to say.
The plan for the bridge construction, Janke said, is to expose the buried
lines and then carefully drive piles.
Its a tight shot because the railroad tracks are elevated
15 to 25 feet above the line, he said. We dont want
the tracks to fall or slide into the excavation.
The entire project is a tight shot, with the railroad tracks and a busy
road on one side and a row of buildings on the other.
|
Project Specs
Project Name: Campus
Drive Bike Path, Phase 1
Location: Madison
Owner: University of Wisconsin-Madison
General Contractor: Janke General Contractors Inc., Athens
Engineer: MSA Professional Services, Madison
Project Cost: $1.21 million
Start Date: August 2007
Scheduled Completion: January 2008
|
Its all difficult because of the access, Janke said.
East of the Walnut Street bridge, were in a 20-foot corridor
between the railroad tracks and the buildings.
Take all of those factors and mix them with the timing of the job coinciding
almost perfectly with the return of university students for the fall semester,
and a simple bike path turns into a dangerous, time-consuming project.
Whenever we move equipment, we dont know who could be standing
there with iPods on their heads and not even hearing you, Janke
said.
But, as the project heads into fall, Janke said his team is dealing with
all the challenges and is targeting the start of November for completion
of the bridge and the retaining walls that will run along a large portion
of the path.
We knew what we were getting into, he said. A slip
of the wrist, and someone could get hurt. Were using extra safety
on this one.
— Chris Thompson
|