
Bentley
squeezes in for Eastcastle Place | The
Yale building meets its end during The Bentley Company's second phase of work
at Eastcastle Place in Milwaukee.
Photos courtesy of The Bentley Company |
If
only the gate was a little wider. Only Don Schliepp truly knows how often
he wishes for width while thinking of the 24-foot opening that provides the only
access point to the Eastcastle Place project on Milwaukees east side. Everyday,
said Schliepp, The Bentley Companys project superintendent on the job. The
biggest challenge is stocking the job and keeping the material readily available. We
knew it would be an issue, and there are days when we wish we could do more, but
we physically cant. And Bentley has plenty to do. The contractor
signed on last year to provide renovations and new construction to portions of
the six-building Eastcastle Place campus, an elderly care facility formerly known
as Milwaukee Protestant Home. The campus sits on an estimated city block-sized
lot bordered by St. Marys Hospital and Downer, Prospect and Bradford avenues. When
you look at it from above, were building a large project on a postage stamp-sized
site, Schliepp said. Bentley approached the project in four phases,
and the first focused on rerouting power and utilities from the Yale building
on the campus. The rerouting was necessary because the second phase called for
the demolition of Yale, a phase that Bentleys team tackled in spring. With
Yale out of the way, Schliepp said, the third phase called for the construction
of the projects centerpiece, which is a 142,000-square-foot, four-story
building with underground parking and 59 independent-living apartments. That phase,
featuring a mix of precast, masonry, wood frames and poured foundation walls,
has presented an entirely new round of challenges.  | The
Bentley Company digs deep to stabilize a neighboring historic structure.
Photos
courtesy of The Bentley Company |
One contractor
cant finish all their work, Schliepp said. Its so intertwined.
The masonry cant finish all the walls until the precast is done. The carpenters
cant do their work until the precast is done. Its a disjointed schedule. But
as the end of August nears, he said, the framing of the building should be about
three-quarters complete, which means the project team is closing in on the fourth
and final phase. That portion of the job calls for an interior gut and
remodel of the historic Milwaukee Protestant Home into 23 new independent-living
apartments. It also includes a remodeling of three floors of the Bradford Terrace
building into skilled nursing and community-based residential facility space. Its
going along very well, Schliepp said. The project is where it should
be. It would be nice to move ahead, but sometimes you just cant. Weve
had contractors willing to work together. We havent had to break up any
fights or anything. - Chris Thompson Project
Specs Project
Name: Eastcastle Place Location: Milwaukee General Contractor/Construction
Manager: The Bentley Company, Milwaukee Architects: AG Architecture Inc., Wauwatosa,
and Kahler Slater Architects, Milwaukee Start Date: October 2004 Scheduled
Completion: June 2007 Project
Fact The
sum total of earth excavated and hauled away from the Eastcastle Place project
would cover Lambeau Field in 12 feet of dirt. |
|